# 772101240518
Unscheduled inspection
Start date: 2021-10-25, end date: 2021-11-19, duration: 18
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100780920
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100399090
Unscheduled inspection
Start date: 2021-08-02, end date: 2021-08-25, duration: 18
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100294929
Unscheduled inspection
Start date: 2021-06-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100173455
Unscheduled inspection
Start date: 2021-05-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100063181
Unscheduled inspection
Start date: 2021-03-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100008210
Unscheduled inspection
Start date: 2021-02-16, end date: 2021-03-02, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772005215150
Unscheduled inspection
Start date: 2020-11-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004427442
Unscheduled inspection
Start date: 2020-06-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004373928
Unscheduled inspection
Start date: 2020-03-30, end date: 2020-04-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, the subject of verification is the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code compliance with the performance of works and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such works with the requirements of design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used