# 662101506610
Unscheduled inspection
Start date: 2021-12-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 662101442081
Unscheduled inspection
Start date: 2021-12-13, end date: 2021-12-24, duration: 10
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to verify compliance with the requirements of Regulation No. 29-14-29/59 dated 05/31/2021 issued by Neofit LLC, the purpose of this inspection is to carry out regional state construction supervision. The subject of this audit is: the fulfillment of the previously issued instruction on the elimination of identified violations of mandatory requirements dated 05/31/2021 No. 29-14-29/59, issued by Neofit LLC.
# 662101168632
Unscheduled inspection
Start date: 2021-10-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 662101262429
Unscheduled inspection
Start date: 2021-10-05, end date: 2021-10-18, duration: 10
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to verify compliance with the requirements of Regulation No. 29-16-29/546 dated 08/13/2021, issued by LLC "Spetstsemremont", the purpose of this inspection is to carry out regional state construction supervision. The subject of this audit is: the fulfillment of the previously issued instruction on the elimination of identified violations of mandatory requirements dated 08/13/2021 No. 29-16-29/546, issued by LLC "Spetstsemremont".
# 662100497564
Unscheduled inspection
Start date: 2021-08-24, end date: 2021-09-06, duration: 10
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to control the execution of a previously issued instruction on the elimination of identified violations; Tasks - the implementation of regional state construction supervision; Subject - the implementation of a previously issued instruction on the elimination of an identified violation of mandatory requirements
# 662100345965
Unscheduled inspection
Start date: 2021-07-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 662100322534
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 662100207417
Unscheduled inspection
Start date: 2021-05-14, end date: 2021-06-04, duration: 16
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program No. 29-17-01/185-17 -4 dated 2020-10-27; Tasks are to carry out regional state construction supervision; The subject is to verify the compliance of work and applicable building materials during the construction of a capital construction facility: A building attached to an existing administrative building (No. 1 according to GP) with an integrated underground parking lot (No. 1A according to GP), located at: Sverdlovsk region, Yekaterinburg, Dobrolyubova str., 10, the results of such work to the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements (with the exception of capital construction projects for which energy efficiency requirements they do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources; the availability of a construction permit; and compliance with the requirements established by parts 2, 3, and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 662100210220
Unscheduled inspection
Start date: 2021-05-31, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 662100157306
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-05-14, duration: 14
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to verify the arguments of the appeal to the court. No. 29-01-01-9219/1 dated 04/08/2021; Tasks - implementation of regional state construction supervision; Subject - verification of the conformity of work and construction materials used during the construction of the capital construction facility "Multi-apartment single-section apartment building (No. 1 according to ROM) with a roof-mounted gas boiler room and an integrated underground parking lot, transformer substation (No. 2 according to ROM), GRPS (No. 3 on ROM)", located at 59 Roshchinskaya St., Yekaterinburg, as well as the results of such work to the requirements of sanitary and epidemiological rules and regulations, safety rules and state standards, and project documentation.
# 662100108448
Unscheduled inspection
Start date: 2021-04-15, end date: 2021-04-28, duration: 10
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to verify compliance with the requirements of Regulation No. 29-16-29/25 dated 02/17/2021, issued by
LLC "Spettsemremont", the purpose of this audit is to carry out regional state construction supervision.
The subject of this audit is: the fulfillment of the previously issued instruction on the elimination of identified violations of mandatory requirements
dated 02/17/2021 No. 29-16-29/25, issued by LLC "Spetstsemremont"
# 662100037352
Unscheduled inspection
Start date: 2021-03-03, end date: 2021-03-26, duration: 17
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to verify compliance with the requirements of Regulation No. 29-14-22/140 dated 12/04/2020, issued by Spetstsemremont LLC. The purpose of this inspection is to carry out regional state construction supervision.
The subject of this audit is: the fulfillment of the previously issued instruction on the elimination of identified violations of mandatory requirements dated 04.12.2020 No. 29-14-22/140, issued by LLC "Spetstsemremont".
# 662100037491
Unscheduled inspection
Start date: 2021-03-03, end date: 2021-03-26, duration: 17
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program No. 29-17-01/185-17 -4 dated 10/27/2020 (Amendment No. 1), the purpose of this inspection is to carry out regional state construction supervision.
The subject of this audit is: verification of the conformity of the work performed and the building materials used during the construction of the capital construction facility "Building attached to the existing administrative building (No. 1 on GP) with an integrated underground parking lot (No. 1A on GP)", located at the address: Sverdlovsk region, Yekaterinburg, Dobrolyubova str., 10, as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation) and (or) the information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities, which are not subject to energy efficiency requirements) and the requirements for equipping a capital construction facility with metering devices for energy resources used; availability of a construction permit; meeting the requirements set out in parts 2, 3 and 3.1 Articles 52 of the Urban Planning Code of the Russian Federation.
# 662105305314
Unscheduled inspection
Start date: 2021-01-19, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 662004466263
Unscheduled inspection
Start date: 2020-07-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 662004407345
Unscheduled inspection
Start date: 2020-05-12, end date: 2020-05-29, duration: 14
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the inspection program 29170118517 3 dated 20190607 Tasks implementation of regional state construction supervision The subject is to verify the compliance of the work and applicable building materials during the construction of a capital construction facility A building attached to the existing administrative building 1 at the GP with a built-in underground parking 1A at the GP located at the address Sverdlovsk region Yekaterinburg Dobrolyubova St. 10 the results of such work with the requirements of the approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code. the Code of the Russian Federation
# 661904004596
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-12-13, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: 6 To establish that this inspection is being conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707535p2 dated September 06, 2019. The objectives of this inspection are to carry out regional state construction supervision.7 The subject of this inspection is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707535p2 dated September 06, 2019
# 661903991226
Unscheduled inspection
Start date: 2019-11-25, end date: 2019-12-06, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Purpose to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707852 dated November 15, 2019 Task implementation of state construction supervision Subject to the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707852 dated November 15, 2019
# 661903979347
Unscheduled inspection
Start date: 2019-11-13, end date: 2019-12-05, duration: —
Authority: Gosudarstvennaya inspekciya truda v Sverdlovskoi oblasti
Purpose of inspection: implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms in connection with information about violations of labor protection requirements identified during the inspection of the materials of the investigation of the accident with Kasimov AG and entailing the threat of harm to the life and health of employees motivated submission 66879619I
# 661903953530
Unscheduled inspection
Start date: 2019-11-13, end date: 2019-11-26, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued instruction on the elimination of identified violations of mandatory requirements 291607614P dated July 17, 2019. The objectives of this audit are to carry out regional state construction supervision. The purpose of this audit is to comply with the previously issued instruction on the elimination of identified violations of mandatory requirements 291607614P dated July 17, 2019.
# 661903953529
Unscheduled inspection
Start date: 2019-11-13, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 661903363424
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-09-20, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Purpose to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707436 P dated July 19, 2019 Task to carry out state construction supervision Subject to the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707436 P dated July 19, 2019
# 661903678336
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-04, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements dated July 09, 2019 291307328 P The objectives of this audit are the implementation of regional state construction supervision The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements dated July 09, 2019 291307328 P
# 661902886148
Unscheduled inspection
Start date: 2019-07-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661902823891
Unscheduled inspection
Start date: 2019-07-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661902849726
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-17, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued instruction on the elimination of identified violations of mandatory requirements 291607238P dated April 19, 2019. The objectives of this audit are to carry out regional state construction supervision. The purpose of this audit is to comply with the previously issued instruction on the elimination of identified violations of mandatory requirements 291607238P dated April 19, 2019.
# 661902808210
Unscheduled inspection
Start date: 2019-06-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661902764949
Unscheduled inspection
Start date: 2019-06-24, end date: —, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:
# 661902678279
Unscheduled inspection
Start date: 2019-05-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661902646779
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-17, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Purpose to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707138 P2 dated March 07, 2019 Task implementation of state construction supervision Subject to the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707138 P2 dated March 07, 2019
# 661902574426
Unscheduled inspection
Start date: 2019-04-08, end date: 2019-04-12, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: purpose to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 29170745p dated February 15, 2019 task implementation of regional state construction supervision subject to the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 29170745p dated February 15, 2019
# 661902571695
Unscheduled inspection
Start date: 2019-03-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661902550198
Unscheduled inspection
Start date: 2019-03-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661902502422
Unscheduled inspection
Start date: 2019-02-11, end date: 2019-02-12, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707781 P2 dated November 23, 2018 The task is to carry out state construction supervision The subject is to comply with the previously issued order to eliminate the identified violation of mandatory requirements 291707781 P2 dated November 23, 2018
# 661902440687
Unscheduled inspection
Start date: 2019-01-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661802127911
Unscheduled inspection
Start date: 2018-11-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661802018967
Unscheduled inspection
Start date: 2018-11-13, end date: 2018-11-23, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291407292 dated June 04, 2018. The purpose of this audit is to carry out regional state construction supervision. The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291407292 dated June 04, 2018.
# 661802127666
Unscheduled inspection
Start date: 2018-11-19, end date: 2018-12-14, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707642P dated October 08, 2018. The objectives of this audit are to implement The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707642P dated October 08, 2018
# 661801910947
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-26, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The inspection is carried out in order to implement the inspection program dated January 29, 2018 29170118517 2. The objectives of this inspection are to carry out regional state construction supervision. The subject of this inspection is to verify the compliance of the work and construction materials used in the construction of the capital construction facility "Building attached to the existing administrative building 1 on GP with a built-in underground parking 1A on GP" located at 10 Dobrolyubova St., Yekaterinburg, Sverdlovsk Region, the results of such work meet the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 661801406012
Unscheduled inspection
Start date: 2018-09-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661800546450
Unscheduled inspection
Start date: 2018-07-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 661800528156
Unscheduled inspection
Start date: 2018-07-09, end date: 2018-07-27, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707320 dated May 31, 2018. The objectives of this audit are to carry out regional state construction supervision. The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707320 dated May 31, 2018.
# 661800564004
Unscheduled inspection
Start date: 2018-07-20, end date: 2018-07-23, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707390 P dated June 15, 2018 The task is to carry out state construction supervision The subject is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291707390 P dated June 15, 2018
# 661800492727
Unscheduled inspection
Start date: 2018-06-22, end date: 2018-07-09, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: Purpose to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291705277 p dated May 18, 2018 Task implementation of state construction supervision Subject to the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291705277 p dated May 18, 2018
# 661800351405
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-31, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the Inspection Program correction 29170118517 2 dated January 29, 2018. The objectives of this inspection are to carry out regional state construction supervision. The subject of this inspection is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Building attached to the existing administrative building 1 on GP with a built-in underground parking 1A on GP" located at 10 Dobrolyubova Street, Yekaterinburg, Sverdlovsk Region, the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 661800227720
Unscheduled inspection
Start date: 2018-03-23, end date: 2018-04-16, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: implementation of regional state construction supervision the inspection is carried out in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 29170755P dated February 12, 2018to conduct an inspection in relation to the limited liability company Spectsemremont 7 The subject of this inspection is the fulfillment of the previously issued order to eliminate the identified violation of mandatory requirements 29170755P dated February 12, 2018
# 66170802930205
Unscheduled inspection
Start date: 2017-12-05, end date: 2017-12-08, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291705P2739 P dated October 20, 2017 Task is to carry out state construction supervision Subject to the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291705P2739 P dated October 20, 2017
# 66170802164797
Unscheduled inspection
Start date: 2017-09-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 66170701810643
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-26, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the arguments of the appeal from 30062017 bx 290101171001 on the production of noisy construction work, including at night
# 66170701456053
Unscheduled inspection
Start date: 2017-03-15, end date: 2017-03-24, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291705c79 p dated January 18, 2017. The objectives of this audit are to carry out regional state construction supervision. The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291705c79 p dated January 18, 2017
# 66170701452869
Unscheduled inspection
Start date: 2017-03-14, end date: 2017-04-10, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements dated February 17, 2017 29130238 the objectives of this audit are the implementation of regional state construction supervision The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements dated February 17, 2017 29130238
# 66170701480477
Unscheduled inspection
Start date: 2017-03-29, end date: 2017-03-31, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The inspection is carried out in order to monitor the execution of the previously issued order to eliminate the identified violation of mandatory requirements 291704P267 P2 dated February 10, 2017. The subject of this inspection is the fulfillment of the previously issued order to eliminate the identified violation of mandatory requirements 291704P267 P2 dated February 10, 2017. The purpose of this inspection is to carry out state construction supervision
# 66170701278567
Unscheduled inspection
Start date: 2017-01-12, end date: 2017-01-13, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The inspection is carried out in order to monitor the execution of the previously issued order to eliminate the identified violation of mandatory requirements 291704P2760 P dated December 02, 2016. The subject of this inspection is the fulfillment of the previously issued order to eliminate the identified violation of mandatory requirements 291704P2760 P dated December 02, 2016. The purpose of this inspection is to carry out state construction supervision
# 66170701285654
Unscheduled inspection
Start date: 2017-01-11, end date: 2017-02-01, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291704c7743 p2 dated November 28, 2016. The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291704c7743 p2 dated November 28, 2016. The purpose of this audit is to carry out state construction supervision
# 72160701098796
Unscheduled inspection
Start date: 2016-11-09, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 66160701099014
Unscheduled inspection
Start date: 2016-11-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72160700936879
Unscheduled inspection
Start date: 2016-10-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 66160700913936
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-09-30, duration: —
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: This inspection is carried out in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 291704c7522 p2 dated August 18, 20166the purpose of this inspection is to comply with the previously issued order to eliminate the identified violation of mandatory requirements 291704c7522 p2 dated August 18, 2016The task of this inspection is to carry out state construction supervision
# 72160700040047
Unscheduled inspection
Start date: 2016-08-19, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: