# 142100670623
Unscheduled inspection
Start date: 2021-09-16, end date: 2021-09-27, duration: 8
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: inspections in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia), on May 12, 2021, compliance with the construction of a capital construction facility by the developer, technical customer, construction contractor, mandatory requirements in the field of construction and applied building materials (products), the established procedure for construction, reconstruction of the facility capital construction.
# 142100311768
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:
# 142105299414
Unscheduled inspection
Start date: 2021-01-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142005153095
Unscheduled inspection
Start date: 2020-10-12, end date: 2020-10-23, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142005153093
Unscheduled inspection
Start date: 2020-10-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142005153091
Unscheduled inspection
Start date: 2020-10-12, end date: 2020-10-23, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 the fulfillment of the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation as prescribed
# 142004446076
Unscheduled inspection
Start date: 2020-07-10, end date: 2020-07-23, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142004446068
Unscheduled inspection
Start date: 2020-07-10, end date: 2020-07-23, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program