# 161904047142
Unscheduled inspection
Start date: 2019-12-03, end date: 2019-12-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the completed works, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of verification of the completed construction facility in accordance with the received by notification to the Inspection dated 27112019 12037 on the completion of the construction of the capital construction facility, the tasks of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements requirements and or requirements established by municipal legal acts
# 161904053590
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations design documentation other regulations norms and rules, as well as to draw up an act on the elimination of violations on the basis of a notice received by the Inspection dated 28112019 12144 on the elimination of violations during the construction reconstruction of a capital construction facility that was ordered to be eliminated within the time limit set by the regulation from 22112019 1712029001 to 06122019 Tasks The purpose of this audit is to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The purpose of this audit is to comply with the instructions of state control bodies, supervision bodies of municipal control
# 161903994628
Unscheduled inspection
Start date: 2019-11-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903966163
Unscheduled inspection
Start date: 2019-11-13, end date: 2019-12-10, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: The purpose of the audit is to protect the rights and interests of employees on the basis of ch7 st360 of the Labor Code of the Russian Federation Tasks of verification ensuring compliance with and protection of labor rights and freedoms of citizens ensuring compliance by the employer with labor legislation and other regulatory legal acts containing norms of labor law Subject to verification compliance with mandatory requirements or requirements established by municipal legal acts
# 161802419192
Unscheduled inspection
Start date: 2018-12-18, end date: 2019-01-22, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Respublike Tatarstan
Purpose of inspection: this inspection is carried out in order to fulfill the Instructions of Deputy Prime Minister A. V. Gordeev dated 28112018 g AGP118385 Rosselkhoznadzor Order dated 4122018 1398 DSP The objectives of this inspection are to monitor compliance by business entities with regulatory requirements in the field of grain quality and safety compliance with rules and regulations for quarantine of plants engaged in production storage in pm and grain of the intervention fund processing and The subject of this inspection is to note the necessary compliance with mandatory requirements or requirements established by municipal legal acts, carrying out measures to prevent harm to the life and health of citizens, harm to animals, plants and the environment
# 161801791547
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the completed works, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of verification of the completed construction facility in accordance with with the notification received by the Inspection dated 25092018 7011 on the completion of the construction of the capital construction facility, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161801791185
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the completed works, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of verification of the completed construction facility in accordance with with the notification received by the Inspection dated 25092018 7009 on the completion of the construction of the capital construction facility, the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800250756
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to establish compliance with the requirements of part 5 of Article 52 of the Urban Planning Code of the Russian Federation as well as to determine the compliance of the completed works used in the construction of an object of capital construction of building materials, the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for used energy resources, the availability of a permit for construction of compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation on the basis of the notification received by the Inspection on the start of construction of a capital construction facility dated 22032018 1881, the objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of a capital construction facility according to the requirements of technical regulations, other regulatory legal acts and project documentation, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800250725
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to establish compliance with the requirements of part 5 of Article 52 of the Urban Planning Code of the Russian Federation as well as to determine the compliance of the completed works used in the construction of an object of capital construction of building materials, the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for used energy resources, the availability of a permit for construction of compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation on the basis of the notification received by the Inspection on the start of construction of a capital construction facility dated 23032018 1880, the objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of a capital construction facility according to the requirements of technical regulations, other regulatory legal acts and project documentation, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800009430
Unscheduled inspection
Start date: 2018-02-01, end date: 2018-03-01, duration: —
Authority: Upravlenie gosavtodornadzora po Respublike Tatarstan
Purpose of inspection: execution of the regulation of 25122017 181B
# 16170802947901
Unscheduled inspection
Start date: 2017-12-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170803047464
Unscheduled inspection
Start date: 2017-11-29, end date: 2017-12-25, duration: —
Authority: Upravlenie gosavtodornadzora po Respublike Tatarstan
Purpose of inspection: compliance with the regulation of 18102017 158B suppression of mandatory requirements
# 16160601786397
Unscheduled inspection
Start date: 2016-08-02, end date: 2016-08-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: protection of the rights and interests of employees Letter from the employer 6331716PV dated 15072016
# 16160601483672
Unscheduled inspection
Start date: 2016-02-11, end date: —, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Respublike Tatarstan
Purpose of inspection:
# 00150601250259
Unscheduled inspection
Start date: 2015-10-13, end date: 2015-10-26, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Respublike Tatarstan
Purpose of inspection: Control over the execution of the regulation GPN 134178 on the elimination of violations of mandatory fire safety requirements
# 16150601268176
Unscheduled inspection
Start date: 2015-09-16, end date: 2015-10-13, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Respublike Tatarstan Tatarstan
Purpose of inspection: execution of the Order of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare 641 dated 06082015 "On conducting unscheduled inspections of water supply and sanitation systems in the territory of the Russian Federation" in order to implement the instructions of the Deputy Chairman of the Government of the Russian Federation dated 22072015 DKP9130pr