# 741802199642
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-14, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of work on fire-fighting and sanitary-epidemiological measures, measures for access of low-mobility groups of the population, energy efficiency measures, landscaping after completion of completed works and construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hr 2 3 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741802291952
Unscheduled inspection
Start date: 2018-12-17, end date: 2019-01-21, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the completed facility 2 Availability of a construction permit 3 Compliance with the requirements of hh 2 3 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741802096861
Unscheduled inspection
Start date: 2018-11-19, end date: 2018-11-23, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the roof and fencing installation of elevator equipment upon completion of the work performed installation of outdoor networks during the work and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation 2 Availability of a building permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741801975999
Unscheduled inspection
Start date: 2018-10-31, end date: 2018-11-07, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of reinforced concrete structures of 1516 floors upon completion of the work performed installation of reinforced concrete structures of the technical floor installation of internal engineering systems installation of window and balcony blocks finishing work of the lower floors during the work and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation 2 Availability of permits for construction 3 Meeting the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741801548954
Unscheduled inspection
Start date: 2018-09-28, end date: 2018-10-04, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of reinforced concrete structures of 1314 floors upon completion of the completed work of 1516 floors installation of window and balcony blocks finishing work of the lower floors during the work and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a building permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800637137
Unscheduled inspection
Start date: 2018-08-24, end date: 2018-08-30, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of reinforced concrete structures of 1112 floors upon completion of the completed work of 1314 floors installation of window and balcony blocks finishing work of the lower floors during the work and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a building permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800545849
Unscheduled inspection
Start date: 2018-07-18, end date: 2018-07-24, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of reinforced concrete structures of 910 floors upon completion of the completed work of 1112 floors installation of window and balcony blocks finishing work of the lower floors during the work and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation 2 Availability of a building permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800465903
Unscheduled inspection
Start date: 2018-06-22, end date: 2018-06-28, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of reinforced concrete structures of 78 floors upon completion of the completed work of 910 floors installation of window and balcony blocks finishing work of the lower floors during the work and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a building permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800375942
Unscheduled inspection
Start date: 2018-05-23, end date: 2018-05-29, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of reinforced concrete structures of 56 floors upon completion of the completed work of 78 floors during the course of work with the elimination of violations in accordance with p 344 of the conclusion of the ITU 1990318 of Mstroyexpert LLC and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh Articles 23 and 31 of the Urban Planning Code of the Russian Federation


# 741800204888
Unscheduled inspection
Start date: 2018-03-30, end date: 2018-04-05, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the actual condition of the object 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


Information about inspections