# 341903011842
Unscheduled inspection
Start date: 2019-08-29, end date: 2019-09-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the facility with the requirements of the urban planning legislation of the Russian Federation, including technical regulations and design documentation, the task of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and design documentation. The subject of this audit is compliance with mandatory requirements in relation to the compliance of work and construction materials used in the process construction reconstruction of the capital construction facility as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources, availability of a construction permit, and compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 341802052115
Unscheduled inspection
Start date: 2018-10-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 341801416232
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-09-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to assess the conformity of the Facility with the requirements of regulatory legal acts and project documentation The task is to ensure that the Facility meets the requirements of regulatory legal acts and project documentation The subject is compliance with mandatory requirements regarding the compliance of construction works, their results and the construction materials used with the requirements of regulatory legal acts and project documentation
# 341800473831
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-07-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: the inspection is carried out in order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation as well as energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used, including technical regulations and design documentation the purpose of this inspection is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and design documentation the subject of this audit is compliance with mandatory requirements regarding a compliance of construction works with their results and applied building materials with the requirements of technical regulations of project documentation b availability of a construction permit c compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation