# 001903881764
Unscheduled inspection
Start date: 2019-11-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 342100159486
Unscheduled inspection
Start date: 2021-04-20, end date: 2021-04-30, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: objective: to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, including technical regulations and project documentation;
tasks: prevention, detection and suppression of violations of the legislation of the Russian Federation, including technical regulations and project documentation.
subject: compliance with mandatory requirements regarding:
a) compliance of the execution of works and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and requirements for the equipment of the capital construction facility with metering devices for used energy resources;
b) availability of a construction permit;
c) fulfillment of the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
# 342005238573
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: cel ocenka sootvetstviya deyatelnosti osuschestvlyaemoi na Obekte trebovaniyam gradostroitelnogo zakonodatelstva Rossiiskoi Federacii i proektnoi dokumentaciizadachi preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva Rossiiskoi Federacii i proektnoi dokumentaciipredmet vypolnenie predpisaniya ot 24092020 3005 vydannogo Obschestvu ob ustranenii narushenii dopuschennyh pri stroitelstve Obekta
# 342005238566
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-04, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, including technical regulations and project documentationtasks to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentationsubject compliance with mandatory requirements regarding the conformity of work performed and building materials used during the construction reconstruction of a capital construction facility, as well as the results of such the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 342004436309
Unscheduled inspection
Start date: 2020-06-17, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 001903881764
Unscheduled inspection
Start date: 2019-11-01, end date: 2019-11-08, duration: —
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of a previously issued prescription. The objectives of this audit are to monitor the measures taken by a legal entity to comply with the prescription
# 341902777857
Unscheduled inspection
Start date: 2019-06-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 341902655388
Unscheduled inspection
Start date: 2019-04-18, end date: 2019-04-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: the purpose is to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, the legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, including technical regulations and project documentation tasks prevention detection and suppression of violations of the legislation of the Russian Federation, including technical regulations and project documentation subject compliance with mandatory requirements in relation to compliance of construction works, their results and the applied building materials with the requirements of the project documentation b availability of a building permit c compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation