# 162101398565
Unscheduled inspection
Start date: 2021-12-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162101398777
Unscheduled inspection
Start date: 2021-12-08, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06.10.2021 case No. 17-04-2021/0074.prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. compliance with mandatory requirements and/or requirements established by municipal legal acts;
# 162101396937
Unscheduled inspection
Start date: 2021-12-08, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06.10.2021 case No. 17-04-2021/0075.prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. compliance with mandatory requirements and/or requirements established by municipal legal acts;
# 162101396549
Unscheduled inspection
Start date: 2021-12-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101399344
Unscheduled inspection
Start date: 2021-12-08, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06.10.2021 case No. 17-04-2021/0076.prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. compliance with mandatory requirements and/or requirements established by municipal legal acts;
# 162101396724
Unscheduled inspection
Start date: 2021-12-08, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06.10.2021 case No. 17-04-2021/0073.prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 162100332035
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the completed works, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of inspection of the completed facility, in accordance with the notice received by the Inspectorate dated 07/01/2021 No. 6799 on the completion of the construction of the capital construction facility.
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.;
# 162100168905
Unscheduled inspection
Start date: 2021-04-26, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/25/2021 case no.16-11-2017/0009/1 .
The objectives of this audit are:
prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.
The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162105328524
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004496090
Unscheduled inspection
Start date: 2020-08-25, end date: 2020-08-27, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 19062020 case 1611201700091 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004157861
Unscheduled inspection
Start date: 2020-01-14, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161903003861
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 08032019 case 121120190032the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 161902865768
Unscheduled inspection
Start date: 2019-08-06, end date: 2019-08-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 26042019 case 1611201700091the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts. acts
# 161902740565
Unscheduled inspection
Start date: 2019-05-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902744862
Unscheduled inspection
Start date: 2019-05-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902597705
Unscheduled inspection
Start date: 2019-04-16, end date: 2019-04-16, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules for determining the fact of execution of the order, as well as for the purpose of drawing up an act on the elimination of violations of the order based on the notice received by the Inspectorate from 20032019 2362 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which were ordered to be eliminated within the time limit set by regulation dated 27/122018 1619034802 to 29032019 and the expiration date of the regulation dated 27/122018 1619034802, the deadline for which expires on 29032019 The objectives of this audit are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and The subject of this audit is the fulfillment of the requirements of the state control bodies, supervision of municipal control bodies.
# 161902683510
Unscheduled inspection
Start date: 2019-04-29, end date: 2019-05-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 31082018 case 121120170092 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, carried out during the construction of a capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902562725
Unscheduled inspection
Start date: 2019-03-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902582880
Unscheduled inspection
Start date: 2019-03-19, end date: 2019-03-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 08032019 case 121120190032 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161902475429
Unscheduled inspection
Start date: 2019-01-31, end date: 2019-02-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the fact of fulfillment of the order dated 27/122018 1219133002, the deadline for which expired on 25.012019 27/122018 1219133001, the deadline for which expired on 25.012019 and drawing up an act based on the results of the inspection The objectives of this inspection are to prevent, identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer performed during the construction of the facility The subject of this audit is to select the necessary compliance with the requirements of state control bodies, supervision bodies, and municipal control bodies for capital construction and work requirements of technical regulations, other regulatory legal acts, and project documentation.
# 161802315361
Unscheduled inspection
Start date: 2018-12-25, end date: 2018-12-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 29102018 case 1611201700091the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts. acts
# 161802362899
Unscheduled inspection
Start date: 2018-12-26, end date: 2018-12-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 31082018 case 121120170092 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161801861559
Unscheduled inspection
Start date: 2018-10-05, end date: 2018-10-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program inspections dated 22082018 case 1611201700091 The objectives of this audit are to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of regulatory legal acts and project documentation by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800646145
Unscheduled inspection
Start date: 2018-08-23, end date: 2018-08-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 29032018 case 1611201700091, the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800537380
Unscheduled inspection
Start date: 2018-07-17, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800503499
Unscheduled inspection
Start date: 2018-07-03, end date: 2018-07-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 29032018 case 1611201700091, the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800324380
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 29032018 case 1611201700091, the objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800208213
Unscheduled inspection
Start date: 2018-03-21, end date: 2018-03-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with According to the inspection program dated 26092017 case 1611201700091, the objectives of this inspection are to prevent, identify and suppress violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to comply with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 16170802956125
Unscheduled inspection
Start date: 2017-12-12, end date: 2017-12-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 26092017 case 1611201700091the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, carried out during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities. legal acts
# 16170802773836
Unscheduled inspection
Start date: 2017-10-30, end date: —, duration: —
Authority: —
Purpose of inspection: