Found 5 inspections:

# 472004445920
Unscheduled inspection
Start date: 2020-06-29, end date: 2020-07-27, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 472004411700
Unscheduled inspection
Start date: 2020-05-21, end date: 2020-06-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used to meet the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 472004371097
Unscheduled inspection
Start date: 2020-03-18, end date: 2020-04-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471902644212
Unscheduled inspection
Start date: 2019-04-11, end date: 2019-05-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 47170701317971
Unscheduled inspection
Start date: 2017-01-19, end date: 2017-02-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on the completion of construction The subject of this audit is compliance with mandatory requirements including compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and requirements equipment of the capital construction facility with accounting devices for the energy resources used, compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.