# 001902964840
Unscheduled inspection
Start date: 2019-08-21, end date: 2019-08-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the fulfillment of the previously issued regulation dated 01072019 131183 due date 05082019 The objectives of this audit are 1 to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation 2 to prevent identify and suppress violations of legislation on urban development committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including technical regulations and project documentation The subject of this audit is the fulfillment of the instruction issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region
# 542105294695
Unscheduled inspection
Start date: 2021-01-11, end date: 2021-01-22, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This check is carried out for the purpose of: verifying the fulfillment of the previously issued order dated 09/28/2020 No. 2/1519, the deadline for which expired on 11/20/2020 (hereinafter referred to as the order);
The objectives of this audit are:
– verification of the elimination of violations and the fulfillment of the requirements (measures) specified in the regulation;
The subject of this inspection is:
– execution of Regulation No. 2/1519 dated 09/28/2020 issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region.
# 542005283558
Unscheduled inspection
Start date: 2020-12-22, end date: 2020-12-31, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: The purpose is to verify the fulfillment of the previously issued regulation dated 06102020 1161597, the deadline for which expired on 07122020 hereinafter referred to as prescriptionsproblems to verify the elimination of violations and compliance with the requirements of the measures specified in the prescriptionsubject execution of regulation 1161597 dated 06102020 issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region
# 542004455882
Unscheduled inspection
Start date: 2020-07-13, end date: 2020-07-22, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: Purpose verification of the fulfillment of the previously issued regulation 18536 dated 18052020 deadline 01072020 Tasks verification of the elimination of violations and compliance with the requirements of the measures specified in the regulation Subject of the fulfillment of regulation 18536 dated 18052020 issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region
# 542004369303
Unscheduled inspection
Start date: 2020-03-25, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection:
# 541904142478
Unscheduled inspection
Start date: 2019-12-27, end date: 2020-01-15, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: Verification of the execution of the previously issued regulation 132562 dated 27/12/2019 deadline 09/122019b The basis for the audit is the expiration of the deadline for the execution of the regulation issued by the state construction supervision authority to eliminate the identified violation of mandatory requirements The objectives of this audit are to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation
# 001903956217
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued regulation dated 04102019 112049 deadline 05112019 The objectives of this inspection are 1 to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation The subject of this inspection is the fulfillment of regulation 112049 dated 04102019 issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region
# 001902964840
Unscheduled inspection
Start date: 2019-08-21, end date: 2019-08-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the fulfillment of the previously issued regulation dated 01072019 131183 due date 05082019 The objectives of this audit are 1 to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation 2 to prevent identify and suppress violations of legislation on urban development committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including technical regulations and project documentation The subject of this audit is the fulfillment of the instruction issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region
# 001902572913
Unscheduled inspection
Start date: 2019-03-15, end date: 2019-03-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the fulfillment of the previously issued regulation dated 01022019 11114 deadline 25022019 The objectives of this audit are 1 to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation 2 to prevent identify and suppress violations of legislation on urban development committed by the developer the customer as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including technical regulations and project documentation The subject of this audit is the fulfillment of the instruction issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region