Found 9 inspections:

# 002004314363
Unscheduled inspection
Start date: 2020-03-02, end date: —, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 772004429250
Unscheduled inspection
Start date: 2020-06-11, end date: —, duration:
Authority:
Purpose of inspection:


# 002004314363
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-03, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya predpisaniya ot 16 dekabrya 2019 g 759G3320H104Zadachami nastoyaschei proverki yavlyayutsyaosuschestvlenie kontrolya za prinyatymi yuridicheskim licom merami po ispolneniyu predpisaniya i soblyudeniyu obyazatelnyh trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstvaprinyatie mer po ustraneniyu narushenii obyazatelnyh trebovanii v sluchae ih vyyavleniya i po privlecheniyu k otvetstvennosti lic dopustivshih narusheniya trebovanii Federalnyh zakonov i inyh normativnyh pravovyh aktov7 Predmetom proverki yavlyaetsya vypolnenie predpisaniya organa gosudarstvennogo kontrolya nadzora


# 772004200138
Unscheduled inspection
Start date: 2020-01-20, end date: —, duration:
Authority:
Purpose of inspection:


# 771904062943
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used


# 77160701195763
Unscheduled inspection
Start date: 2016-12-05, end date: 2016-12-09, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77160700886555
Unscheduled inspection
Start date: 2016-09-29, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77160700051971
Unscheduled inspection
Start date: 2016-08-22, end date: 2016-08-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used


# 77160601716745
Unscheduled inspection
Start date: 2016-07-15, end date: 2016-07-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.