# 551903598459
Unscheduled inspection
Start date: 2019-09-19, end date: 2019-10-16, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Omskoi oblasti
Purpose of inspection: verification of the execution of the instruction on the elimination of violations during the construction reconstruction of a capital construction facility issued by the Main Directorate of State Construction Supervision and State Expertise of the Omsk Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development and project documentation committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the technical customer
# 321902673733
Unscheduled inspection
Start date: 2019-04-15, end date: 2019-04-17, duration: —
Authority: Gosudarstvennaya inspekciya truda v Bryanskoi oblasti
Purpose of inspection: The purpose of protecting the rights and interests of employees is to implement a set of measures for federal state supervision of compliance with labor legislation and other regulatory legal acts containing labor law norms 0000000010001244260 Tasks supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms Subject compliance with mandatory requirements or requirements established by municipal legal acts
# 321902507391
Unscheduled inspection
Start date: 2019-02-11, end date: 2019-03-07, duration: —
Authority: Gosudarstvennaya inspekciya truda v Bryanskoi oblasti
Purpose of inspection: The purpose of protecting the rights and interests of employees is to implement a set of measures for federal state supervision of compliance with labor legislation and other regulatory legal acts containing labor law norms 0000000010001244260 Tasks supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms Subject compliance with mandatory requirements or requirements established by municipal legal acts
# 741802153091
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-07, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the execution of the order dated 09/12/2018 with a deadline of 23/12/2018 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 321802341364
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-27, duration: —
Authority: Gosudarstvennaya inspekciya truda v Bryanskoi oblasti
Purpose of inspection: The purpose of protecting the rights and interests of employees is to implement a set of measures for federal state supervision of compliance with labor legislation and other regulatory legal acts containing labor law norms 0000000010001244260 Tasks supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms Subject compliance with mandatory requirements or requirements established by municipal legal acts
# 741802199711
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-14, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of work on the installation of a block complete transformer substation commissioning and construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741802009608
Unscheduled inspection
Start date: 2018-11-05, end date: 2018-11-09, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on landscaping with the installation of a production sewage system installation of an LNG pumping unit an LNG pump unit and the construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741801557923
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741801913253
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-19, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of communication networks of the automated process control system of the evaporator of the atmospheric heater of the gas-electric reinforcement unit of the gas accumulator unit with a steam gas compressor stele information of the LNG tank and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 The Urban Planning Code of the Russian Federation
# 42170802892579
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities
# 42170802713451
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-10-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: The purpose is to verify the compliance of the work performed and the construction materials used in the course of work Tasks compliance with the requirements of the legislation of the Russian Federation on urban planning activities during the construction of the object Subject compliance with the mandatory requirements of the legislation of the Russian Federation on urban planning activities