# 142100196712
Unscheduled inspection
Start date: 2021-03-19, end date: —, duration: 20
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: proverka zakonchennogo stroitelstvom obekta kapitalnogo stroitelstva na a) sootvetstvie postroennogo obekta kapitalnogo stroitelstva trebovaniyam tehnicheskih reglamentov (norm i pravil), inyh normativnyh pravovyh aktov i proektnoi dokumentacii; b) ustranenie zastroischikom, tehnicheskim zakazchikom, licom, osuschestvlyayuschim stroitelstvo, vyyavlennyh pri provedenii stroitelnogo kontrolya i osuschestvlenii gosudarstvennogo stroitelnogo nadzora vseh narushenii sootvetstviya vypolnennyh rabot trebovaniyam proektnoi dokumentacii; v) oformlenie ispolnitelnoi dokumentacii, svyazannoi s vypolneniem vseh rabot po stroitelstvu, a takzhe primeneniem stroitelnyh materialov (izdelii). Po izvescheniyu ob okonchanii stroitelstva Upravleniya gosstroizhilnadzora RS(YA).
# 142100023751
Unscheduled inspection
Start date: 2021-02-20, end date: 2021-02-26, duration: 4
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: 1) sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 Gradostroitelnogo Kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 Gradostroitelnogo Kodeksa Rossiiskoi Federacii), v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; 2) nalichie razresheniya na stroitelstvo; 3) vypolnenie trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii.
Po predpisanii i po izvescheniyu ob ustranenii predpisaniya, prodlennogo po sroku ustraneniya po hodataistvom
# 142005252047
Unscheduled inspection
Start date: 2020-12-02, end date: 2020-12-29, duration: 20
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: proverka zakonchennogo stroitelstvom obekta kapitalnogo stroitelstva na a sootvetstvie postroennogo obekta kapitalnogo stroitelstva trebovaniyam tehnicheskih reglamentov norm i pravil inyh normativnyh pravovyh aktov i proektnoi dokumentacii b ustranenie zastroischikom tehnicheskim zakazchikom licom osuschestvlyayuschim stroitelstvo vyyavlennyh pri provedenii stroitelnogo kontrolya i osuschestvlenii gosudarstvennogo stroitelnogo nadzora vseh narushenii sootvetstviya vypolnennyh rabot trebovaniyam proektnoi dokumentacii v oformlenie ispolnitelnoi dokumentacii svyazannoi s vypolneniem vseh rabot po stroitelstvu a takzhe primeneniem stroitelnyh materialov izdelii Po izvescheniyu ob okonchanii stroitelstva Upravleniya gosstroizhilnadzora RSYA
# 142005252097
Unscheduled inspection
Start date: 2020-12-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142005196620
Unscheduled inspection
Start date: 2020-10-29, end date: 2020-11-12, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142004443087
Unscheduled inspection
Start date: 2020-07-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141903990844
Unscheduled inspection
Start date: 2019-11-21, end date: 2019-12-04, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 141903021139
Unscheduled inspection
Start date: 2019-09-03, end date: 2019-09-17, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 141801855961
Unscheduled inspection
Start date: 2018-10-09, end date: 2018-10-22, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 141801964548
Unscheduled inspection
Start date: 2018-10-16, end date: 2018-10-19, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, 1 compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 6 of Article 52 of the Urban Planning Code of the Russian Federation By prescription and by notification of elimination
# 141800620227
Unscheduled inspection
Start date: 2018-08-15, end date: 2018-08-31, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii 1 na sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 nalichie razresheniya na stroitelstvo 3vypolnenie trebovanii chastei 236 stati 52 Gradostroitelnogo kodeksa RF nalichie svidetelstva o dopuske k rabotam po stroitelstvu rekonstrukcii kotorye okazyvayut vliyanie na bezopasnost obektov kapitalnogo stroitelstva v tom chisle svidetelstva o dopuske k rabotam po organizacii stroitelstvo v sluchae privlecheniya zastroischikom ili tehnicheskim zakazchikom na osnovanii dogovora fizicheskogo ili yuridicheskogo lica
# 14170701792813
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-08-11, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation1, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor, to ensure that the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, comply with the requirements of technical regulations and project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 the availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation the availability of a certificate of admission to construction and reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by the developer or the technical customer on the basis of the contract of the natural or legal person According to the program of inspections
# 14160700994876
Unscheduled inspection
Start date: 2016-10-18, end date: 2016-10-25, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, for compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by a developer or a technical customer on the basis of an agreement between an individual or a legal entity under the inspection program
# 14150601448509
Unscheduled inspection
Start date: 2015-01-21, end date: 2015-02-04, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Respublike Saha YAkutiya
Purpose of inspection: on the execution of the prescription
# 14150601448500
Unscheduled inspection
Start date: 2015-01-21, end date: 2015-02-04, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Respublike Saha YAkutiya
Purpose of inspection: on the execution of the prescription