# 261802169112
Unscheduled inspection
Start date: 2018-11-27, end date: 2018-12-24, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: The objectives of the inspection notification dated 23112018 185320114 on completion of construction Inspection program dated 30112017 26072017 Final inspection of the completion of the inspection the objectives of this inspection are to prevent identify and suppress violations of the legislation on urban development by the developer, the technical customer, the person carrying out construction, including technical regulations and project documentation the subject of the inspection is compliance with the procedure for conducting construction control, maintaining general and or special work logs executive documentation preparation of acts of inspection of works of structures of sections of engineering and technical support networks elimination of violations of compliance of completed works with the requirements of technical regulations norms and rules of other normative legal acts and project documentation identified during construction control and implementation of regional state construction supervision, further violations as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations compliance with other requirements when performing works established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used, compliance with mandatory requirements and or requirements established by municipal legal acts
# 261801947675
Unscheduled inspection
Start date: 2018-10-12, end date: 2018-11-08, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: The objectives of the inspection notification dated 04102018 156870114 on the elimination of violations notification dated 04102018 156860114 on the completion of construction Inspection program dated 30112017 26072017 Final inspection of the completion of the inspection the objectives of this inspection are to prevent identify and suppress violations of the legislation on urban development by the developer, the technical customer, the person carrying out construction, including technical regulations and project documentation subject of verification compliance with the procedure for conducting construction control maintenance of general and or special logs of works of executive documentation preparation of acts of inspection of works of structures of sections of engineering and technical support networks elimination of violations of compliance of completed works with the requirements of technical regulations norms and rules of other normative legal acts and project documentation identified during construction control and implementation of regional state construction supervision, violations of compliance with technical regulations norms and rules of other normative legal acts and project documentation, hereinafter violations, as well as compliance with the prohibition to proceed with the continuation of work before drawing up acts on the elimination of such violations compliance with other requirements when performing work established by the project documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used compliance with mandatory requirements and or requirements established by municipal legal acts
# 261800660716
Unscheduled inspection
Start date: 2018-08-24, end date: 2018-09-20, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: The objectives of the audit notification dated 09082018 124510114 on the execution of the previously issued prescription dated 09072018 26072017 the objectives of the audit the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the technical customer, the person carrying out construction, including technical regulations and project documentation the subject of the audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 261800507855
Unscheduled inspection
Start date: 2018-07-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 261800236374
Unscheduled inspection
Start date: 2018-03-26, end date: 2018-04-23, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: The objectives of the audit are the expiration of the deadline for the execution of the order on the elimination of identified violations from 18012018 26072017 The objectives of the audit the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and project documentation The subject of the audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 26170802966109
Unscheduled inspection
Start date: 2017-12-11, end date: —, duration: —
Authority: —
Purpose of inspection: