Found 4 inspections:

# 052105320335
Unscheduled inspection
Start date: 2021-01-27, end date: 2021-02-17, duration: 1
Authority: Ministerstvo stroitelstva i zhilischno-kommunalnogo hozyaistva Respubliki Dagestan
Purpose of inspection: prevention, detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of project documentation performed during the construction and reconstruction of capital construction facilities and compliance with the requirements of Article 54 of the Urban Planning Code of the Russian Federation, in accordance with the program of inspections of the facility for 2021


# 052005246785
Unscheduled inspection
Start date: 2020-11-24, end date: —, duration:
Authority: Ministerstvo stroitelstva i zhilischnokommunalnogo hozyaistva Respubliki Dagestan
Purpose of inspection:


# 052004283531
Unscheduled inspection
Start date: 2020-02-12, end date: 2020-03-12, duration:
Authority: Ministerstvo stroitelstva i zhilischnokommunalnogo hozyaistva Respubliki Dagestan
Purpose of inspection: The purpose is to prevent identify and suppress violations of compliance of works performed during construction and reconstruction of capital construction facilities with the requirements of project documentation and compliance with the requirements of Article 54 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections of the facility for 2020. The purpose of this audit is to verify compliance of the work performed with the requirements of the project other normative acts of the Russian Federation and normative legal acts of federal executive authorities that are subject to mandatory execution during the construction and reconstruction of capital construction facilities Tasks of inspection review of executive documentation verification of compliance of work and construction materials used during construction reconstruction as well as the results of such work with the requirements of project documentation


# 051902966694
Unscheduled inspection
Start date: 2019-08-15, end date: 2019-09-05, duration:
Authority: Ministerstvo stroitelstva i zhilischnokommunalnogo hozyaistva Respubliki Dagestan
Purpose of inspection: prevention, detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of project documentation performed during the construction and reconstruction of capital construction facilities and compliance with the requirements of Article 54 of the Urban Planning Code of the Russian Federation in accordance with the program of providence inspections of the facility for 2019


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.