# 161902717328
Unscheduled inspection
Start date: 2019-05-20, end date: 2019-05-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 12112018 case 171120180044the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation7 carried out by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation7the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902541552
Unscheduled inspection
Start date: 2019-03-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161802309790
Unscheduled inspection
Start date: 2018-12-18, end date: 2018-12-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 22112018 1719028601, the deadline for which expired on 12/122018, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out reconstruction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulations performed during the construction of a capital construction facility. regulatory legal acts and project documentation 7 The subject of this audit is to select the necessary compliance with the regulations of state control bodies, supervision bodies of municipal control
# 161802309683
Unscheduled inspection
Start date: 2018-12-18, end date: 2018-12-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the reconstruction of the capital construction facility comply with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 12112018 case 171120180044 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility by the developer, customer, or person carrying out reconstruction on the basis of a contract with the developer or customer. 7 The subject of this inspection is to select the necessary compliance with mandatory requirements and or the requirements established by municipal legal acts