Found 23 inspections:

# 001902756467
Unscheduled inspection
Start date: 2019-06-13, end date: —, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 262101222398
Unscheduled inspection
Start date: 2021-10-15, end date: —, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: The purpose of the inspection is the inspection program dated 07/02/2021 No. 26/07-2021. Stage 3; objectives of the audit - the objectives of this audit are to prevent, identify and suppress violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, technical customer, and construction contractor; the subject of the audit is compliance with the procedure for conducting construction control, maintaining general and (or) special work logs, and executive documentation, drawing up acts of inspection of works, structures, sections of engineering and technical support networks; - compliance with the compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved design documentation; - compliance with mandatory requirements and/or requirements established by municipal legal acts.


# 262100677981
Unscheduled inspection
Start date: 2021-09-08, end date: —, duration:
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection:


# 262100905459
Unscheduled inspection
Start date: 2021-09-22, end date: —, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: The purpose of the inspection is the inspection program dated 07/02/2021 No. 26/07-2021. Stage 2; objectives of the audit - the objectives of this audit are to prevent, identify and suppress violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, technical customer, and construction contractor; the subject of the audit is compliance with the procedure for conducting construction control, maintaining general and (or) special work logs, and executive documentation, preparation of acts of inspection of works, structures, sections of engineering and technical support networks; - compliance with the compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the approved design documentation; - compliance with mandatory requirements and/or requirements established by municipal legal acts.


# 262004425083
Unscheduled inspection
Start date: 2020-06-01, end date: 2020-06-29, duration:
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: this inspection is carried out for the purpose of the inspection program from 07032018 23032018 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out the construction, compliance with other requirements when performing work established by the project documentation, including energy efficiency and equipment requirements The subject of this audit is compliance with the procedure for conducting construction control, maintaining general and or special logs of work, executive documentation, and drawing up certificates of work inspection of structures of sections of engineering and technical support networks.


# 261904098526
Unscheduled inspection
Start date: 2019-10-16, end date: —, duration:
Authority:
Purpose of inspection:


# 261903303661
Unscheduled inspection
Start date: 2019-09-10, end date: —, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection:


# 261902800900
Unscheduled inspection
Start date: 2019-07-01, end date: —, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection:


# 001902756467
Unscheduled inspection
Start date: 2019-06-13, end date: 2019-06-14, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: to assess compliance with Rostechnadzor Order No. 15032017 85 "On inspections of organizations operating tower cranes" based on the instruction of Deputy Prime Minister of the Russian Federation AG Khloponin dated 08022017 AHP9682 "On the organization and conduct of unscheduled inspections of organizations operating Tower cranes from 2017 to 2019"


# 261902756596
Unscheduled inspection
Start date: 2019-06-04, end date: —, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection:


# 001902561383
Unscheduled inspection
Start date: 2019-03-12, end date: 2019-03-13, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 6 To establish that this audit is being conducted in order to assess compliance with Rostechnadzor Order No. 15032017 85 "On Inspections of organizations operating Tower cranes" based on instructions from Deputy Prime Minister of the Russian Federation AG Khloponin dated 08022017 AHP9682 "On the organization and conduct of unscheduled inspections of organizations operating Tower cranes from 2017 to 2019" The objectives of this audit are a prevention detection and suppression of violations of mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial safety and technical regulation of mandatory requirements b taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of federal laws and other regulatory legal acts


# 261802210224
Unscheduled inspection
Start date: 2018-12-06, end date: 2018-12-28, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: This inspection is carried out with the purpose of notification dated 23112018 185380114 of Stroyservice OJSC on the completion of works subject to inspection in accordance with the inspection program dated 02102018 21062018 stage 1 the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer, the technical customer, and the person carrying out construction, including technical regulations and project documentation. The subject of this inspection is compliance with the procedure for conducting construction control, maintaining general and or special logs of work, executive documentation, drawing up certificates of inspection of work on structures, sections of engineering and technical support networks, compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used, compliance with mandatory requirements and or requirements established by municipal legal acts


# 261802081348
Unscheduled inspection
Start date: 2018-11-13, end date: 2018-12-10, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: This inspection is carried out for the purpose of notification dated 01112018 173100114 of Stroyservice OJSC on the completion of works subject to inspection in accordance with the inspection program dated 25012017 21022017 stage 3 the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer, the technical customer, the person carrying out construction, including technical regulations and project documentation. The subject of this inspection is compliance with the procedure for conducting construction control, maintaining general and or special logs of work, executive documentation, drawing up certificates of inspection of work on structures, sections of engineering and technical support networks, compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used, compliance with mandatory requirements and or requirements established by municipal legal acts


# 261800655607
Unscheduled inspection
Start date: 2018-09-10, end date: —, duration:
Authority:
Purpose of inspection:


# 261800472740
Unscheduled inspection
Start date: 2018-07-02, end date: —, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection:


# 261800514471
Unscheduled inspection
Start date: 2018-06-27, end date: 2018-07-24, duration:
Authority: Gosudarstvennaya inspekciya truda v Stavropolskom krae
Purpose of inspection: Protection of the rights and interests of employees in connection with the consideration of the appeal


# 001800464614
Unscheduled inspection
Start date: 2018-05-30, end date: 2018-06-09, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of JSC Stroyservice's compliance with the mandatory requirements of legislative, regulatory and regulatory technical documents in the field of industrial safety of technical devices of buildings and structures and documentation of state control over compliance with legal requirements based on the operational message of JSC Stroyservice vh dated 25052018 6061A1 and a reasoned submission from the senior state inspector of the interregional Department of State Construction Supervision for supervision of self-regulating organizations and lifting facilities The mechanisms of Borodienko Vladimir Vasilyevich dated 28052018, the tasks of this audit are the prevention detection and suppression of violations of mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial safety and technical regulation of mandatory requirements


# 261800193944
Unscheduled inspection
Start date: 2018-03-16, end date: —, duration:
Authority:
Purpose of inspection:


# 26170803009870
Unscheduled inspection
Start date: 2017-12-21, end date: 2018-01-25, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: This inspection is carried out for the purpose of notifying Stroyservice OJSC on 13122017 176810114 of the completion of works subject to inspection in accordance with the inspection program dated 16022017 2104201the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out the construction. The subject of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts


# 26170803017198
Unscheduled inspection
Start date: 2017-12-22, end date: 2018-01-26, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: This audit is conducted with the purpose of notifying Stroyservice OJSC to conduct a final audit in accordance with the inspection program from 16022017 to 21042017the objectives of this audit are to prevent, identify and suppress violations of urban planning legislation by the developer, technical customer, and the person carrying out construction, including technical regulations and project documentation. The subject of this audit is to comply with mandatory requirements and or requirements established by municipal legal acts


# 26170802634260
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-31, duration:
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: This inspection is carried out with the purpose of notification dated 22092017 135550114 on the completion of works subject to inspection in accordance with the inspection program dated 09112015 21042015the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer, the technical customer, and the person carrying out construction, including technical regulations and project documentation. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts. acts


# 26170802623888
Unscheduled inspection
Start date: 2017-09-29, end date: —, duration:
Authority:
Purpose of inspection:


# 26170801911191
Unscheduled inspection
Start date: 2017-08-22, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.