# 001800383443
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-06-18, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu kontrolya vypolneniya ranee vydannogo predpisaniya ot 11 dekabrya 2017 g 3519PKIP383 pp 1 12 srok ispolneniya kotorogo istek zadachami nastoyaschei proverki yavlyayutsya kontrol za ispolneniem ranee vydannogo predpisaniya ot 11 dekabrya 2017 g 3519PKIP383 pp 1 12 srok ispolneniya kotorogo istek Predmetom nastoyaschei proverki yavlyaetsya vypolnenie predpisaniya dolzhnostnogo lica Sibirskogo upravleniya Rostehnadzora ot 11 dekabrya 2017 g 3519PKIP383 pp 1 12 srok ispolneniya kotorogo istek
# 00170802885579
Unscheduled inspection
Start date: 2017-11-14, end date: 2017-12-11, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celkontrol vypolneniya ranee vydannogo predpisaniya ot 15092017 3519POZP227 punkty 120srok ispolneniya kotorogo istekzadachikontrol za ispolneniem ranee vydannogo predpisaniya ot 15092017 3519POZP227 punkty 120predmet proverkivypolnenie predpisaniya dolzhnostnogo lica Sibirskogo upravleniya Rostehnadzora ot 15092017 3519POZP227 punkty 120srok ispolneniya kotorogo istek
# 00170801910956
Unscheduled inspection
Start date: 2017-08-21, end date: 2017-09-15, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the readiness of the heat supply organization to work in the autumn-winter period of 2017-2018, checking the safe operation and technical condition of power plants of the main and auxiliary equipment of boiler houses