# 142100405069
Unscheduled inspection
Start date: 2021-07-22, end date: —, duration: 7
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: 1) compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Planning Code of the Russian Federation), including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for energy resources used; 2) availability of a construction permit; 3) compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
According to the inspection program
# 142100320527
Unscheduled inspection
Start date: 2021-06-15, end date: —, duration: 8
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: 1) compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Planning Code of the Russian Federation), including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for energy resources used; 2) availability of a construction permit; 3) compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
According to the inspection program
# 142100207623
Unscheduled inspection
Start date: 2021-05-19, end date: 2021-06-01, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu: proverki v sootvetstvii s programmoi proverok utverzhdennoi 1-m zamestitelem rukovoditelya Upravleniya gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya), 25 fevralya 2021 g., soblyudeniya pri stroitelstve obekta kapitalnogo stroitelstva zastroischikom, tehnicheskim zakazchikom, licom, osuschestvlyayuschim stroitelstvo, obyazatelnyh trebovanii v oblasti stroitelstva i primenyaemyh stroitelnyh materialov (izdelii), ustanovlennogo poryadka stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva; , preduprezhdenie, vyyavlenie i presechenie dopuschennyh zastroischikom, tehnicheskim zakazchikom, a takzhe licom, osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom (dalee - podryadchik), narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, v tom chisle proektnoi dokumentacii., soblyudenie obyazatelnyh trebovanii i (ili) trebovanii, ustanovlennyh municipalnymi pravovymi aktami; sootvetstvie svedenii, soderzhaschihsya v uvedomlenii o nachale osuschestvleniya otdelnyh vidov predprinimatelskoi deyatelnosti, obyazatelnym trebovaniyam; sootvetstvie svedenii, soderzhaschihsya v zayavlenii i dokumentah yuridicheskogo lica ili individualnogo predprinimatelya o predostavlenii pravovogo statusa, specialnogo razresheniya (licenzii) na pravo osuschestvleniya otdelnyh vidov deyatelnosti ili razresheniya (soglasovaniya) na osuschestvlenie inyh yuridicheski znachimyh deistvii, esli provedenie sootvetstvuyuschei vneplanovoi proverki yuridicheskogo lica, individualnogo predprinimatelya predusmotreno pravilami predostavleniya pravovogo statusa, specialnogo razresheniya (licenzii), vydachi razresheniya (soglasovaniya) obyazatelnym trebovaniyam, a takzhe dannym ob ukazannyh yuridicheskih licah i individualnyh predprinimatelyah, soderzhaschimsya v edinom gosudarstvennom reestre yuridicheskih lic, edinom gosudarstvennom reestre individualnyh predprinimatelei i drugih federalnyh informacionnyh resursah; vypolnenie predpisanii organov gosudarstvennogo kontrolya (nadzora), organov municipalnogo kontrolya; provedenie meropriyatii: po predotvrascheniyu prichineniya vreda zhizni, zdorovyu grazhdan, vreda zhivotnym, rasteniyam, okruzhayuschei srede, obektam kulturnogo naslediya (pamyatnikam istorii i kultury) narodov Rossiiskoi Federacii, muzeinym predmetam i muzeinym kollekciyam, vklyuchennym v sostav Muzeinogo fonda Rossiiskoi Federacii, osobo cennym, v tom chisle unikalnym, dokumentam Arhivnogo fonda Rossiiskoi Federacii, dokumentam, imeyuschim osoboe istoricheskoe, nauchnoe, kulturnoe znachenie, vhodyaschim v sostav nacionalnogo bibliotechnogo fonda; po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera; po obespecheniyu bezopasnosti gosudarstva; po likvidacii posledstvii prichineniya takogo vreda.
# 142100207503
Unscheduled inspection
Start date: 2021-05-19, end date: 2021-06-01, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: proverki v svyazi s postupivshim v Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya) izvescheniem fakticheskogo ustraneniya pri stroitelstve obekta kapitalnogo stroitelstva vyyavlennyh ranee narushenii, predpisannyh k ustraneniyu ranee vydannym predpisaniem (vh. №2935 ot 30.04.2021 ), preduprezhdenie, vyyavlenie i presechenie dopuschennyh zastroischikom, tehnicheskim zakazchikom, a takzhe licom, osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom (dalee - podryadchik), narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, v tom chisle proektnoi dokumentacii., soblyudenie obyazatelnyh trebovanii i (ili) trebovanii, ustanovlennyh municipalnymi pravovymi aktami; sootvetstvie svedenii, soderzhaschihsya v uvedomlenii o nachale osuschestvleniya otdelnyh vidov predprinimatelskoi deyatelnosti, obyazatelnym trebovaniyam; sootvetstvie svedenii, soderzhaschihsya v zayavlenii i dokumentah yuridicheskogo lica ili individualnogo predprinimatelya o predostavlenii pravovogo statusa, specialnogo razresheniya (licenzii) na pravo osuschestvleniya otdelnyh vidov deyatelnosti ili razresheniya (soglasovaniya) na osuschestvlenie inyh yuridicheski znachimyh deistvii, esli provedenie sootvetstvuyuschei vneplanovoi proverki yuridicheskogo lica, individualnogo predprinimatelya predusmotreno pravilami predostavleniya pravovogo statusa, specialnogo razresheniya (licenzii), vydachi razresheniya (soglasovaniya) obyazatelnym trebovaniyam, a takzhe dannym ob ukazannyh yuridicheskih licah i individualnyh predprinimatelyah, soderzhaschimsya v edinom gosudarstvennom reestre yuridicheskih lic, edinom gosudarstvennom reestre individualnyh predprinimatelei i drugih federalnyh informacionnyh resursah; vypolnenie predpisanii organov gosudarstvennogo kontrolya (nadzora), organov municipalnogo kontrolya; provedenie meropriyatii: po predotvrascheniyu prichineniya vreda zhizni, zdorovyu grazhdan, vreda zhivotnym, rasteniyam, okruzhayuschei srede, obektam kulturnogo naslediya (pamyatnikam istorii i kultury) narodov Rossiiskoi Federacii, muzeinym predmetam i muzeinym kollekciyam, vklyuchennym v sostav Muzeinogo fonda Rossiiskoi Federacii, osobo cennym, v tom chisle unikalnym, dokumentam Arhivnogo fonda Rossiiskoi Federacii, dokumentam, imeyuschim osoboe istoricheskoe, nauchnoe, kulturnoe znachenie, vhodyaschim v sostav nacionalnogo bibliotechnogo fonda; po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera; po obespecheniyu bezopasnosti gosudarstva; po likvidacii posledstvii prichineniya takogo vreda.
# 142100040705
Unscheduled inspection
Start date: 2021-03-05, end date: 2021-03-19, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: 1) compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 Urban Planning Code of the Russian Federation), including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for energy resources used; 2) availability of a construction permit; 3) compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.
According to the inspection program
# 142005246987
Unscheduled inspection
Start date: 2020-11-30, end date: 2020-12-11, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the prescription and notification of the elimination of the prescription
# 142005246984
Unscheduled inspection
Start date: 2020-11-30, end date: 2020-12-11, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142005194854
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-11-16, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Respublike Saha YAkutiya
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms
# 142004443019
Unscheduled inspection
Start date: 2020-06-25, end date: 2020-07-08, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142004440303
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-07-06, duration: 8
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including among the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation According to the inspection program
# 142004227129
Unscheduled inspection
Start date: 2020-01-24, end date: 2020-01-31, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii1 sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 nalichiya razresheniya na stroitelstvo 3 vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 31 6 stati 52 Gradostroitelnogo Kodeksa RF
# 14170801988924
Unscheduled inspection
Start date: 2017-09-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 14170701771322
Unscheduled inspection
Start date: 2017-07-13, end date: 2017-07-24, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the conformity of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work for the organization of construction in case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity