# 77180803166395
Unscheduled inspection
Start date: 2018-06-20, end date: 2018-06-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803119546
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-04-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803088979
Unscheduled inspection
Start date: 2018-02-21, end date: 2018-03-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701694108
Unscheduled inspection
Start date: 2017-06-06, end date: 2017-06-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701547875
Unscheduled inspection
Start date: 2017-04-14, end date: 2017-04-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor, compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701375611
Unscheduled inspection
Start date: 2017-02-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701288548
Unscheduled inspection
Start date: 2016-12-30, end date: 2016-12-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used