# 161800602425
Unscheduled inspection
Start date: 2018-10-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161801477573
Unscheduled inspection
Start date: 2018-09-18, end date: 2018-09-18, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 08082018 1619019801, the deadline for which expired on January 100, 2018, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulations performed during the construction of a capital construction facility. regulatory legal acts and project documentation The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800602284
Unscheduled inspection
Start date: 2018-08-08, end date: 2018-08-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 28062018 1619015301, the deadline for which expired on 27072018, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulations performed during the construction of a capital construction facility. regulatory legal acts and project documentation The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800487199
Unscheduled inspection
Start date: 2018-07-02, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161800487110
Unscheduled inspection
Start date: 2018-06-28, end date: 2018-07-03, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program dated 28042018 case 1618201401243, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800451464
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-06-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of fulfillment of the order dated 06/122017 1619052501, the deadline for which expired on 01062018, and to draw up an act based on the results of the inspection. The objectives of this inspection are to prevent, identify and suppress violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulations performed during the construction of a capital construction facility. regulatory legal acts and project documentation The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800371446
Unscheduled inspection
Start date: 2018-05-18, end date: 2018-05-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with according to the inspection program from 10052018 case 1618201401244, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800308269
Unscheduled inspection
Start date: 2018-04-25, end date: 2018-04-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the Inspection notification dated 16042018 2546 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 21032018 1619006601 to 21052018 The objectives of this audit are to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationthe subject of this audit is to comply with the instructions of state control bodies, supervision bodies, and municipal control bodies.
# 161800205793
Unscheduled inspection
Start date: 2018-03-19, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16170802940017
Unscheduled inspection
Start date: 2017-12-05, end date: 2017-12-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with With the inspection program, the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 16170802955200
Unscheduled inspection
Start date: 2017-12-11, end date: 2017-12-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of inspection of the completed facility in accordance with with the notice received by the Inspection dated 241/12017 9621 on the completion of the construction of the capital construction facility, the objectives of this inspection are to prevent, as well as identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The purpose of this inspection is to comply with mandatory requirements and or requirements established by municipal legal acts
# 16170701391847
Unscheduled inspection
Start date: 2017-02-21, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160701267212
Unscheduled inspection
Start date: 2016-12-27, end date: 2016-12-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of inspection of the completed facility in in accordance with the notice received by the Inspectorate dated 14122016 11395 on the completion of construction reconstruction at the capital construction facility, the prevention, as well as the detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with mandatory requirements