Found 4 inspections:

# 161902471815
Unscheduled inspection
Start date: 2019-02-01, end date: 2019-02-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as to draw up an inspection report on the completed construction of the facility in accordance with the received by notification dated 22.012019 445 to the Inspection on the completion of the construction of the capital construction facility, the objectives of this inspection are to prevent, identify and prevent violations of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the client, the person carrying out the construction on the basis of a contract with the developer or the customer. 7 The subject of this inspection is select the required compliance with mandatory requirements and or requirements established by municipal legal acts


# 161802211923
Unscheduled inspection
Start date: 2018-12-11, end date: 2018-12-17, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 25092018 case 1618201401243 The objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility. The subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 161800910700
Unscheduled inspection
Start date: 2018-09-10, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 161800672879
Unscheduled inspection
Start date: 2018-08-31, end date: 2018-08-31, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to establish compliance with the requirements of Part 5 of Article 52 of the Urban Planning Code of the Russian Federation, as well as to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. construction of compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation on the basis of a notice received by the Inspectorate on the start of construction of a capital construction facility, prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of works performed during the construction of the capital construction facility with the requirements of technical regulations and other regulatory legal acts acts and project documentation compliance with mandatory requirements and or requirements established by municipal legal acts


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.