# 502005182942
Unscheduled inspection
Start date: 2020-08-31, end date: 2020-09-04, duration: 5
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: proverka ispolneniya predpisaniya ot 14072020 0213083000503 ocenka sootvetstviya vypolnyaemyh rabot trebovaniyam proektnoi dokumentacii na obekte kapitalnogo stroitelstva Torgovoofisnoe zdanie po adresu Moskovskaya oblast g Krasnogorsk ul Bratev Gorozhankinyh dom 15
# 142004430236
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 142004322394
Unscheduled inspection
Start date: 2020-03-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004329940
Unscheduled inspection
Start date: 2020-03-10, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 141903923042
Unscheduled inspection
Start date: 2019-11-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141902960456
Unscheduled inspection
Start date: 2019-08-16, end date: 2019-08-29, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in in case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity
# 141902966914
Unscheduled inspection
Start date: 2019-08-20, end date: 2019-08-26, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu fakticheskogo ustraneniya pri stroitelstve obekta kapitalnogo stroitelstva vyyavlennyh ranee narushenii predpisannyh k ustraneniyu predpisaniem 040890918 ot 10 oktyabrya 2018 goda
# 141902955059
Unscheduled inspection
Start date: 2019-08-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141902795318
Unscheduled inspection
Start date: 2019-06-20, end date: 2019-06-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is 1 compliance of the work performed and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 31 6 of Article 52 of the Urban Planning Code of the Russian Federation
# 141801656018
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141801760534
Unscheduled inspection
Start date: 2018-10-02, end date: 2018-10-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is According to the verification program 1 compliance of the work and the construction materials used during the construction of the reconstruction of the capital facility construction as well as the results of such work to the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 141800604975
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-17, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is According to the verification program 1 compliance of the work and the construction materials used during the construction of the reconstruction of the capital facility construction as well as the results of such work to the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 141800273167
Unscheduled inspection
Start date: 2018-04-12, end date: 2018-04-18, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is According to the verification program 1 compliance of the work and the construction materials used during the construction of the reconstruction of the capital facility construction as well as the results of such work to the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 141800248125
Unscheduled inspection
Start date: 2018-04-03, end date: 2018-04-09, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is According to the verification program 1 compliance of the work and the construction materials used during the construction of the reconstruction of the capital facility construction as well as the results of such work to the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 14170701857507
Unscheduled inspection
Start date: 2017-08-08, end date: 2017-08-14, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer and the person carrying out construction on the basis of an agreement with the developer or the customer hereinafter referred to as the contractor, including technical regulations and design documentationthe subject of this audit is according to the verification program1 compliance of the work and the construction materials used in the construction process reconstruction of the capital construction facility as well as the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation
# 14170701857702
Unscheduled inspection
Start date: 2017-08-08, end date: 2017-08-14, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyaFakticheskogo ustraneniya narushenii predpisannyh k ustraneniyu predpisaniem 040855817 ot 28 iyunya 2017 goda1 sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 nalichie razresheniya na stroitelstvo3vypolnenie trebovanii chastei 236 stati 52 Gradostroitelnogo kodeksa RF
# 14170701850711
Unscheduled inspection
Start date: 2017-08-07, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701801823
Unscheduled inspection
Start date: 2017-07-25, end date: 2017-07-28, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is according to the verification program compliance of the work and the construction materials used in the construction process reconstruction of the capital construction facility as well as the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity
# 14170701801790
Unscheduled inspection
Start date: 2017-07-24, end date: 2017-07-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is according to the verification program compliance of the work and the construction materials used in the construction process reconstruction of the capital construction facility as well as the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity
# 14170701707269
Unscheduled inspection
Start date: 2017-06-16, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701707300
Unscheduled inspection
Start date: 2017-06-22, end date: 2017-06-28, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is according to the verification program compliance of the work and the construction materials used in the construction process reconstruction of the capital construction facility as well as the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity
# 76170701601627
Unscheduled inspection
Start date: 2017-05-15, end date: 2017-05-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: kontrol soblyudeniya gradostroitelnogo zakonodatelstva normativnoi dokumentacii v ramkah polnomochii Inspekcii pri provedenii OOO «Vostokzhilstroi» rabot po stroitelstvu obekta kapitalnogo stroitelstva «Mnogokvartirnyi zhiloi dom s inzhenernymi kommunikaciyami 2 etapa g YAroslavl 2ya Novaya v raione d 22 na osnovanii motivirovannogo predstavleniya o provedenii vneplanovoi dokumentarnoi proverki
# 14170701509272
Unscheduled inspection
Start date: 2017-04-07, end date: 2017-04-11, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyaFakticheskogo ustraneniya narushenii predpisannyh k ustraneniyu predpisaniem 0408155916 ot 22 noyabrya 2016 goda1 sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 nalichie razresheniya na stroitelstvo3vypolnenie trebovanii chastei 236 stati 52 Gradostroitelnogo kodeksa RF nalichie svidetelstva o dopuske k rabotam po stroitelstvu rekonstrukcii kotorye okazyvayut vliyanie na bezopasnost obektov kapitalnogo stroitelstva v tom chisle svidetelstva o dopuske k rabotam po organizacii stroitelstvo v sluchae privlecheniya zastroischikom ili tehnicheskim zakazchikom na osnovanii dogovora fizicheskogo ili yuridicheskogo lica
# 14170701555694
Unscheduled inspection
Start date: 2017-04-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 14170701537215
Unscheduled inspection
Start date: 2017-04-20, end date: 2017-04-26, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is according to the verification program compliance of the work and the construction materials used in the construction process reconstruction of the capital construction facility as well as the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in the case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity
# 14170701508935
Unscheduled inspection
Start date: 2017-03-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 14160701113040
Unscheduled inspection
Start date: 2016-11-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 14160701041197
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyaFakticheskogo ustraneniya narushenii predpisannyh k ustraneniyu predpisaniem 040888916 ot 08 avgusta 2016 goda 1 sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov2 nalichie razresheniya na stroitelstvo3vypolnenie trebovanii chastei 236 stati 52 Gradostroitelnogo kodeksa RF nalichie svidetelstva o dopuske k rabotam po stroitelstvu rekonstrukcii kotorye okazyvayut vliyanie na bezopasnost obektov kapitalnogo stroitelstva v tom chisle svidetelstva o dopuske k rabotam po organizacii stroitelstvo v sluchae privlecheniya zastroischikom ili tehnicheskim zakazchikom na osnovanii dogovora fizicheskogo ili yuridicheskogo lica
# 14160601748122
Unscheduled inspection
Start date: 2016-08-03, end date: 2016-08-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and design documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit is the conformity of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work for the organization of construction in case of involvement by the developer or technical customer on the basis of a contract of an individual or legal entity