Found 17 inspections:

# 762101306949
Unscheduled inspection
Start date: 2021-11-11, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Purpose: based on the inspection program; Task: to determine the compliance of the work performed during the construction of the capital construction facility with the requirements of the project documentation Subject: compliance with mandatory requirements


# 762100418271
Unscheduled inspection
Start date: 2021-08-12, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Purpose: based on the inspection program; Task: to determine the compliance of the work performed during the construction of the capital construction facility with the requirements of the project documentation Subject: compliance with mandatory requirements


# 762100190842
Unscheduled inspection
Start date: 2021-05-19, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Purpose: based on the inspection program; Task: to determine the compliance of the work performed during the construction of the capital construction facility with the requirements of the project documentation Subject: compliance with mandatory requirements


# 762100063341
Unscheduled inspection
Start date: 2021-03-19, end date: 2021-03-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Purpose: based on the inspection program; Task: to determine the compliance of the work performed during the construction of the capital construction facility with the requirements of the project documentation Subject: compliance with mandatory requirements


# 762005267746
Unscheduled inspection
Start date: 2020-12-18, end date: 2020-12-18, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Purpose based on the inspection program, the task is to determine the compliance of the work performed during the construction of the capital construction facility with the requirements of the project documentation, the subject is compliance with mandatory requirements


# 762005249255
Unscheduled inspection
Start date: 2020-12-10, end date: 2020-12-18, duration: 8
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: proverka provoditsya s celyu po izvescheniyu ob okonchanii stroitelstva ot2011112020 vh 1683 Zadachami nastoyaschei proverki yavlyayutsya opredelenie sootvetstviya rabot vypolnennyh pri stroitelstve obekta kapitalnogo stroitelstva trebovaniyam proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii


# 762004399862
Unscheduled inspection
Start date: 2020-04-23, end date: 2020-04-23, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of project documentation7 The subject of this audit is compliance with mandatory requirements


# 762004276374
Unscheduled inspection
Start date: 2020-02-11, end date: 2020-02-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of project documentation7 The subject of this audit is compliance with mandatory requirements


# 761904010581
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-11-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation7 The subject of this audit is compliance with mandatory requirements


# 761903413204
Unscheduled inspection
Start date: 2019-09-12, end date: 2019-09-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation7 The subject of this audit is compliance with mandatory requirements


# 761902774526
Unscheduled inspection
Start date: 2019-06-14, end date: 2019-06-14, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements


# 761902595402
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-04-16, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po YAroslavskoi oblasti
Purpose of inspection: cel ispolnenie trebovaniya prokuratury YAroslavskoi oblasti ot 13032019g 7392019 o provedenii vneplanovoi proverki otnositelno uslovii vklyuchaemyh v dogovory uchastiya v dolevom stroitelstve s fizicheskimi licami grazhdanamipotrebitelyami zadachami preduprezhdenie i presechenie narushenii zakonodatelstva o zaschite prav potrebitelei v sfere uchastiya grazhdanpotrebitelei v dolevom stroitelstve predmet soblyudenie obyazatelnyh trebovanii


# 761802414259
Unscheduled inspection
Start date: 2018-12-11, end date: 2018-12-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements


# 761800898767
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration:
Authority:
Purpose of inspection:


# 761802047130
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-11-10, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: proverka provoditsya s celyu na osnovanii izvescheniya ob okonchanii stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva ot 09102018 Vh 1482018 Zadachami nastoyaschei proverki yavlyayutsya opredelenie sootvetstviya postroennogo obekta kapitalnogo stroitelstva trebovaniyam tehnicheskih reglamentov norm i pravil inyh normativnyh pravovyh aktov i proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii


# 761801818978
Unscheduled inspection
Start date: 2018-09-27, end date: 2018-09-27, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements


# 761800353670
Unscheduled inspection
Start date: 2018-05-18, end date: 2018-05-18, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.