# 282005200093
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-11-23, duration: 20
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: verification of the completed facility and the issue of issuing an opinion on the compliance of the constructed facility with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used. execution of the verification program The objectives of this audit are to prevent identify and suppress violations of compliance committed by the developer, the technical customer, the person carrying out construction, performed during the construction of the capital construction facility as well as the results of such work to the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, the subject of this audit is to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and equipment capital construction facility with metering devices for used energy resources
# 282004430304
Unscheduled inspection
Start date: 2020-06-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281904080809
Unscheduled inspection
Start date: 2019-12-03, end date: 2019-12-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v Amurskoi oblasti
Purpose of inspection: This audit is carried out with the aim of implementing federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms consideration of the appeal dated 29112019 g 287322119 on violations of labor legislation requirements including labor protection requirements that entailed the threat of harm to the life and health of employees not conducting a special assessment of working conditions as well as on the facts of evasion from The objectives of this audit are supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 281904041972
Unscheduled inspection
Start date: 2019-12-05, end date: 2020-01-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: verification of the completed facility and the issue of issuing an opinion on the compliance of the constructed facility with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources implementation of the inspection program approved on 28/122018 The objectives of this audit are to prevent identify and suppress violations of compliance by the developer technical customer person carrying out construction performed during the construction of the facility The purpose of this audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment for the capital construction facility with metering devices for energy resources used. The purpose of this audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources
# 281903902241
Unscheduled inspection
Start date: 2019-10-29, end date: 2019-11-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: execution of the inspection program approved on 28/122018the objectives of this audit are to prevent identify and suppress violations committed by the developer, the technical customer, and the person carrying out construction of violations of compliance with the requirements of the capital construction facility performed during construction, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used. The purpose of this audit is to verify compliance with the requirements of the capital construction facility. works and construction materials used during the construction of the capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 281902870266
Unscheduled inspection
Start date: 2019-07-16, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection:
# 281902753994
Unscheduled inspection
Start date: 2019-05-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281902658442
Unscheduled inspection
Start date: 2019-04-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281902451691
Unscheduled inspection
Start date: 2019-01-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281902451151
Unscheduled inspection
Start date: 2019-01-23, end date: 2019-02-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: execution of the inspection program approved on 28/12/2018 The objectives of this inspection are to prevent identify and suppress violations committed by the developer, the technical customer, and the person carrying out the construction of violations of compliance with the requirements of the capital construction facility performed during construction, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used. The subject of this inspection is to verify compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used