Found 8 inspections:

# 221801737836
Unscheduled inspection
Start date: 2018-09-25, end date: —, duration:
Authority:
Purpose of inspection:


# 221800500303
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-06-27, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: the purpose of verifying the information contained in the inspection program 1 The objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the technical customer, including the requirements of technical regulations and project documentation. The subject of this audit is ch2 st54 GrK RF to verify the conformity of work performed and construction materials used during the construction of the reconstruction of a capital construction facility, as well as the results of the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, compliance with the mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal Law No. 30122009 384 FZ "Technical Regulations on the Safety of Buildings and Structures"


# 221800413671
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-05-28, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: To establish that this audit is being conducted in connection with the expiration of the deadline for ZAPSIBSTROY LLC to comply with the GIA14GSN regulation issued by the State Inspectorate of the Altai Territory dated 25042018. The objectives of this audit are to prevent identify and suppress violations of the law on urban development by the person carrying out the construction, including the requirements of technical regulations and project documentation. The subject of this audit is st51 GrK RF ch2 st54 GrK RF verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the mandatory requirements for a construction permit and the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code Russian Federation Federal Law No. 30122009384FZ "Technical Regulations on the Safety of Buildings and Structures


# 221800311187
Unscheduled inspection
Start date: 2018-04-25, end date: 2018-04-25, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: The inspection is carried out in order to verify the information contained in the collective appeal of residents of the house on Ulmaloolonskaya 29 in Gbarnaul dated 23032018 bx 0109o1553 dated 23032018 and gr Demyanenko IV dated 11042018 bx 31OG112 dated 11042018 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the person carrying out the construction, including the requirements of technical regulations and project documentation. The purpose of this audit is st51 GrK RF ch2 st54 GrK RF verification of the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal Law No. 30122009384FZ "Technical Regulations on the Safety of Buildings and Structures


# 22180803055537
Unscheduled inspection
Start date: 2018-01-12, end date: 2018-01-12, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: in order to verify the information contained in the notice on the elimination of violations 6 dated 28/122017 bx dated 29/122017 specified in the act of inspection of the completed facility K124GSN dated 13122017, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, including the requirements of technical regulations and project documentation. The subject of this audit is ch2 st54 GrK RF conformity assessment performance of works and construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, requirements of technical regulations, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with mandatory requirements for a construction permit and the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal The law of 30122009 384FZ "Technical regulations on the safety of buildings and structures"


# 22170802972581
Unscheduled inspection
Start date: 2017-12-12, end date: 2017-12-13, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: in order to verify the information contained in the notice of completion of construction 5 dated 05/122017 BX 31VP6192 dated 06/122017, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, including the requirements of technical regulations and project documentationthe subject of this audit is ch2 st54 GRK RF checking the compliance of the work and the construction materials used during the construction and reconstruction of the facility capital construction, as well as the results of such work, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources, compliance with the mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal Law No. 30122009 384 FZ "Technical Regulations on the Safety of Buildings and Structures structures"


# 22170802224887
Unscheduled inspection
Start date: 2017-09-08, end date: 2017-09-08, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: in order to verify the information contained in the notice dated 04072017 3 vx 31VP3369 dated 06072017 on the completion dates of the works subject to verification, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, including the requirements of technical regulations and project documentationthe subject of this audit is ch2 st54 GRK RF checking the compliance of the work and the construction materials used in the process the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal Law No. 30122009 384 FZ "Technical Regulations on safety of buildings and structures


# 22170701463646
Unscheduled inspection
Start date: 2017-03-16, end date: 2017-03-16, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: the purpose of the program of inspections is to prevent identify and suppress violations of legislation on urban development activities the subject is to verify the completed construction of the facility, verify compliance of the work and construction materials used in the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements of equipment of the capital construction facility with metering devices used compliance with the mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.