# 772100450323
Unscheduled inspection
Start date: 2021-08-13, end date: 2021-08-20, duration: 6
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: to carry out control measures in connection with the receipt of the developer's (customer's) notification; The objectives of the audit: to prevent, identify and suppress violations of the requirements of project documentation and legislation on urban development by the person being audited; The subject of the audit: to verify the elimination of violations specified in the order issued by Mosgosstroynadzor, the conformity of work performed and the construction materials used in the process construction, reconstruction of the capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance with the requirements of the project documentation identified during construction control and state construction supervision.
# 772100341410
Unscheduled inspection
Start date: 2021-07-14, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100253986
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-25, duration: 14
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision