Found 4 inspections:

# 161800252768
Unscheduled inspection
Start date: 2018-04-06, end date: 2018-04-10, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The purpose of the inspection is to determine whether the construction materials used in the construction and reconstruction of the capital construction facility and the results of such work comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as to draw up an inspection report on the completed construction of the facility in accordance with with the notice received by the Inspection on the completion of the construction of the capital construction facility, the task of the inspection is to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of the inspection is compliance with mandatory requirements or requirements established by the Legislation of the Russian Federation. municipal legal acts


# 16170701326228
Unscheduled inspection
Start date: 2017-01-30, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 16160700862759
Unscheduled inspection
Start date: 2016-10-03, end date: 2016-10-06, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The purpose of the audit the audit is carried out in order to determine the compliance of the performed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used The task of verification is to prevent as well as identify and suppress violations committed by the developer customer the person carrying out construction on the on the basis of an agreement with the developer or the customer for violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation Subject to verification compliance with mandatory requirements or requirements established by municipal legal acts


# 16160601791009
Unscheduled inspection
Start date: 2016-08-16, end date: 2016-08-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The purpose of the audit the audit is carried out in order to determine the compliance of the performed works used in the process of construction reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used The task of verification is to prevent as well as identify and suppress violations committed by the developer customer the person carrying out construction on the on the basis of an agreement with the developer or the customer for violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation Subject to verification compliance with mandatory requirements or requirements established by municipal legal acts


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.