# 362005082878
Unscheduled inspection
Start date: 2020-10-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 361903889937
Unscheduled inspection
Start date: 2019-10-22, end date: 2019-11-19, duration: —
Authority: Gosudarstvennaya inspekciya truda v Voronezhskoi oblasti
Purpose of inspection: this audit is conducted in order to consider an employee's request for violation of his labor rights. The objectives of this audit are to ensure compliance and protection of labor rights and freedoms of citizens, including the right to safe working conditions, ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 361902683053
Unscheduled inspection
Start date: 2019-05-27, end date: 2019-05-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the fulfillment of a previously issued instruction to eliminate identified violations. The objectives of this audit are to prevent identify and suppress violations of urban planning legislation committed by the developer, the technical customer, as well as by the person carrying out construction and reconstruction on the basis of a contract with the developer or the technical customer, including the requirements of project documentation. The subject of this audit is to comply with the instructions of state control bodies supervision of municipal control bodies
# 361902480654
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-03-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to verify the fulfillment of a previously issued instruction on the elimination of identified violations. The objectives of this audit are to prevent, identify and suppress violations of urban planning legislation committed by the developer, the technical customer, as well as the person carrying out construction and reconstruction on the basis of an agreement with the developer or the technical customer, including the requirements of project documentation. The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies
# 361802284029
Unscheduled inspection
Start date: 2018-12-17, end date: 2018-12-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the start of construction reconstruction The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including the requirements of project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer. The purpose of the audit is to comply with mandatory requirements or requirements established by municipal legal acts