# 772005221751
Unscheduled inspection
Start date: 2020-11-13, end date: 2020-11-26, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the audit program The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772005178992
Unscheduled inspection
Start date: 2020-10-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004486904
Unscheduled inspection
Start date: 2020-08-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004455509
Unscheduled inspection
Start date: 2020-07-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004420363
Unscheduled inspection
Start date: 2020-06-01, end date: 2020-06-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 772004412793
Unscheduled inspection
Start date: 2020-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004377898
Unscheduled inspection
Start date: 2020-03-30, end date: 2020-03-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772004313945
Unscheduled inspection
Start date: 2020-03-10, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004269565
Unscheduled inspection
Start date: 2020-02-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004294404
Unscheduled inspection
Start date: 2020-02-18, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004206782
Unscheduled inspection
Start date: 2020-01-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004216451
Unscheduled inspection
Start date: 2020-01-21, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 771904047405
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program. The tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person. The subject is to verify the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for used energy resourcesperformance by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code
# 77180803268774
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803249113
Unscheduled inspection
Start date: 2018-10-11, end date: 2018-10-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803216586
Unscheduled inspection
Start date: 2018-08-31, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803195705
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-08-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803188773
Unscheduled inspection
Start date: 2018-07-26, end date: 2018-07-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803188755
Unscheduled inspection
Start date: 2018-07-27, end date: 2018-07-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803167381
Unscheduled inspection
Start date: 2018-06-22, end date: 2018-06-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803142867
Unscheduled inspection
Start date: 2018-05-18, end date: 2018-05-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803148151
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803122942
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803089006
Unscheduled inspection
Start date: 2018-02-26, end date: 2018-02-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803066747
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170803000379
Unscheduled inspection
Start date: 2017-12-12, end date: 2017-12-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802901823
Unscheduled inspection
Start date: 2017-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802800001
Unscheduled inspection
Start date: 2017-10-27, end date: 2017-10-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802638863
Unscheduled inspection
Start date: 2017-09-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701519412
Unscheduled inspection
Start date: 2017-04-11, end date: 2017-04-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160700824725
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii istecheniya sroka ispolneniya yuridicheskim licom individualnym predprinimatelem vydannogo organom gosudarstvennogo stroitelnogo nadzora predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovaniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentacii proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 747116 ot 05082016
# 77160601743316
Unscheduled inspection
Start date: 2016-07-11, end date: 2016-08-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the capital construction facility with the requirements of technical regulations and project documentation based on the approved inspection program
# 77160601714831
Unscheduled inspection
Start date: 2016-07-11, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: