# 112202027982
Unscheduled inspection
Start date: 2022-04-18, end date: 2022-04-29, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Purpose: To conduct an inspection in accordance with the inspection program
Verification tasks:
Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, including project documentationsubject:
Compliance with mandatory requirements
# 112202011636
Unscheduled inspection
Start date: 2022-04-18, end date: 2022-04-29, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Purpose: To conduct an inspection in accordance with the inspection program
Verification tasks:
Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, including project documentationsubject:
Compliance with mandatory requirements
# 112202011298
Unscheduled inspection
Start date: 2022-04-18, end date: 2022-04-29, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Purpose: To conduct an inspection in accordance with the inspection program
Verification tasks:
Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, including project documentationsubject:
Compliance with mandatory requirements
# 112201991394
Unscheduled inspection
Start date: 2022-04-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112201851327
Unscheduled inspection
Start date: 2022-02-14, end date: 2022-02-25, duration: 9
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Purpose: To conduct an inspection in accordance with the inspection program
Verification tasks:
Prevention, detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentationsubject, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer:
Compliance with mandatory requirements
# 112201850653
Unscheduled inspection
Start date: 2022-02-14, end date: —, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection:
# 112202006909
Unscheduled inspection
Start date: 2022-02-14, end date: 2022-02-25, duration: 9
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Purpose: To conduct an inspection in accordance with the inspection program
Verification tasks:
Prevention, detection and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, including project documentationsubject:
Compliance with mandatory requirements
# 112201843949
Unscheduled inspection
Start date: 2022-01-24, end date: 2022-01-31, duration: 6
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Purpose: To conduct an inspection in accordance with the inspection program
Verification tasks:
Prevention, detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentationsubject, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer:
Compliance with mandatory requirements
# 112201839181
Unscheduled inspection
Start date: 2022-01-24, end date: —, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection:
# 112201843260
Unscheduled inspection
Start date: 2022-01-24, end date: 2022-01-31, duration: 6
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Purpose: To conduct an inspection in accordance with the inspection program
Verification tasks:
Prevention, detection and suppression of violations of the legislation on urban planning activities, including technical regulations and project documentationsubject, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer:
Compliance with mandatory requirements
# 112201644565
Unscheduled inspection
Start date: 2022-01-17, end date: 2022-01-28, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Verification of the execution of the Regulation on the elimination of violations of mandatory requirements No. 17 dated 10.12.2021 (until 01/15/2022), requesting documents, receiving written explanations, Checking the execution of the Order to eliminate violations of mandatory requirements No. 17 dated 12/10/2021. (deadline is 15.01.2022)
# 112201644280
Unscheduled inspection
Start date: 2022-01-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112201562176
Unscheduled inspection
Start date: 2022-01-18, end date: 2022-01-31, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting an inspection in connection with the occurrence of an event specified in the inspection program, preventing, detecting and suppressing violations of urban planning legislation by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, including project documentation, Compliance with mandatory requirements provided for in paragraphs 1-5) Part 3 of Article 54 of the Urban Planning Code of the Russian Federation
# 112101537984
Unscheduled inspection
Start date: 2021-12-20, end date: 2021-12-29, duration: 8
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting an inspection in connection with the occurrence of an event specified in the inspection program, preventing, detecting and suppressing violations of legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, Compliance with mandatory requirements
# 112101537185
Unscheduled inspection
Start date: 2021-12-20, end date: 2021-12-29, duration: 8
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting an inspection in connection with the occurrence of an event specified in the inspection program, preventing, detecting and suppressing violations of legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, Compliance with mandatory requirements
# 112101393944
Unscheduled inspection
Start date: 2021-11-22, end date: 2021-11-30, duration: 7
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting inspections in accordance with the inspection program, preventing, detecting and suppressing violations of legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, compliance with mandatory requirements
# 112101000625
Unscheduled inspection
Start date: 2021-10-04, end date: 2021-10-08, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting an inspection in accordance with the inspection program, , compliance with mandatory requirements
# 112101000231
Unscheduled inspection
Start date: 2021-10-04, end date: 2021-10-08, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting an inspection in accordance with the inspection program, Compliance with mandatory conditions
# 112100999601
Unscheduled inspection
Start date: 2021-10-04, end date: 2021-10-08, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting an inspection in accordance with the inspection program, , compliance with mandatory requirements
# 112101001015
Unscheduled inspection
Start date: 2021-10-04, end date: 2021-10-08, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting an inspection in accordance with the inspection program, , compliance with mandatory requirements
# 112100973141
Unscheduled inspection
Start date: 2021-10-04, end date: 2021-10-08, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting an inspection in accordance with the inspection program, , compliance with mandatory requirements
# 112100973720
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112101266225
Unscheduled inspection
Start date: 2021-10-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112100808175
Unscheduled inspection
Start date: 2021-09-16, end date: —, duration: 7
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Carrying out an inspection of the fulfillment of the previously issued instruction of the state control (supervision) body; Prevention, detection and suppression of violations of the legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; Compliance with mandatory requirements; Compliance with the instructions of state control bodies (supervision), municipal control bodies.
# 112100844878
Unscheduled inspection
Start date: 2021-09-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112100822087
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112100817301
Unscheduled inspection
Start date: 2021-09-20, end date: 2021-09-24, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting inspections in accordance with the inspection program, Preventing, detecting and suppressing violations of legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, Compliance with mandatory requirements
# 112100825473
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection:
# 112100820179
Unscheduled inspection
Start date: 2021-09-20, end date: 2021-09-24, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting inspections in accordance with the inspection program, preventing, detecting and suppressing violations of legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, Compliance with mandatory requirements
# 112100847625
Unscheduled inspection
Start date: 2021-09-20, end date: 2021-09-24, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting inspections in accordance with the inspection program, Preventing, detecting and suppressing violations of legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, Compliance with mandatory requirements
# 112100853512
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: 5
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Conducting inspections in accordance with the inspection program; preventing, detecting and suppressing violations of urban planning legislation, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; Compliance with mandatory requirements.
# 112100282577
Unscheduled inspection
Start date: 2021-06-15, end date: —, duration: 11
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting inspections in accordance with the inspection program; preventing, detecting and suppressing violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; compliance with mandatory requirements
# 112100281675
Unscheduled inspection
Start date: 2021-06-15, end date: 2021-07-02, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting inspections in accordance with the inspection program, preventing, identifying and suppressing violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or technical customer, compliance with mandatory requirements
# 112100275774
Unscheduled inspection
Start date: 2021-06-15, end date: 2021-07-02, duration: 11
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting inspections in accordance with the inspection program, preventing, identifying and suppressing violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or technical customer, compliance with mandatory requirements
# 112100268136
Unscheduled inspection
Start date: 2021-06-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112100196163
Unscheduled inspection
Start date: 2021-05-12, end date: 2021-05-27, duration: 12
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Verification of the execution of regulation No. 8 dated 04/06/2021, prevention, detection and suppression of violations of legislation on urban development, including project documentation, by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, compliance with the regulations of state control (supervision), municipal control bodies
# 112100254365
Unscheduled inspection
Start date: 2021-05-12, end date: 2021-05-27, duration: 12
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Verification of the execution of regulation No. 8 dated 04/06/2021, prevention, detection and suppression of violations of legislation on urban development, including project documentation, by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, compliance with the regulations of state control (supervision), municipal control bodies
# 112100157937
Unscheduled inspection
Start date: 2021-04-16, end date: 2021-05-05, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Carrying out verification of the fulfillment of previously issued instructions of the state control (supervision) body; Prevention, detection and suppression of violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; Compliance with mandatory requirements; Compliance with regulations bodies of state control (supervision)
# 112100156748
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-04-30, duration: 12
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Carrying out verification of the fulfillment of previously issued instructions of the state control (supervision) body; Prevention, detection and suppression of violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; Compliance with mandatory requirements; Compliance with regulations bodies of state control (supervision)
# 112100156735
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-04-30, duration: 12
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: Carrying out verification of the fulfillment of previously issued instructions of the state control (supervision) body; Prevention, detection and suppression of violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; Compliance with mandatory requirements, compliance with regulations bodies of state control (supervision)
# 112100015611
Unscheduled inspection
Start date: 2021-02-15, end date: 2021-03-01, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting inspections in accordance with the inspection program; preventing, detecting and suppressing violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; compliance with mandatory requirements
# 112100016294
Unscheduled inspection
Start date: 2021-02-15, end date: 2021-03-01, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo, zhilischnogo i tehnicheskogo nadzora (kontrolya)
Purpose of inspection: conducting inspections in accordance with the inspection program; preventing, detecting and suppressing violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer; compliance with mandatory requirements
# 112100015975
Unscheduled inspection
Start date: 2021-02-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 292005264078
Unscheduled inspection
Start date: 2020-11-30, end date: 2020-12-02, duration: 3
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of the fulfillment of the instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of the capital construction facility from 09102020 250316Uh200336 N Verification of the elimination by a legal entity of the violations identified in the instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of the capital construction facility from 09102020 250316Uh200336 N The fulfillment by a legal entity of the instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of the capital construction facility from 09102020 250316Uh200336 P
# 112004506903
Unscheduled inspection
Start date: 2020-08-27, end date: 2020-09-09, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: conducting an inspection in accordance with the inspection program prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the technical customer, compliance with mandatory requirements
# 112004506902
Unscheduled inspection
Start date: 2020-08-21, end date: 2020-09-03, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: Conducting inspections in accordance with the inspection program Compliance with mandatory requirements Prevention detection and suppression of violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer
# 112004455782
Unscheduled inspection
Start date: 2020-07-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 112004380786
Unscheduled inspection
Start date: 2020-01-14, end date: 2020-01-23, duration: 10
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: Purpose verification in accordance with the notice 14 on completion of construction dated 16/12/2019 Subject compliance with mandatory requirements
# 112004170284
Unscheduled inspection
Start date: 2020-01-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 111904160455
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-10-25, duration: 3
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: inspection in accordance with the 19 notice of completion of construction dated 08102019
# 111903864920
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-10-25, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: Objectives Verification in accordance with Notice 19 dated 08/10/2019 on completion of construction Subject Compliance with mandatory requirements compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with in accordance with parts 38 and 39 of Article 49 of this Code and or the information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, meeting the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation dated 29122004 190FZ
# 111904160476
Unscheduled inspection
Start date: 2019-10-22, end date: —, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection:
# 111903782924
Unscheduled inspection
Start date: 2019-10-22, end date: —, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection:
# 111903602440
Unscheduled inspection
Start date: 2019-09-19, end date: —, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection:
# 111903602480
Unscheduled inspection
Start date: 2019-09-19, end date: 2019-09-20, duration: —
Authority: Sluzhba Respubliki Komi stroitelnogo zhilischnogo i tehnicheskogo nadzora kontrolya
Purpose of inspection: Objectives Verification in accordance with the inspection program Subject to Compliance with mandatory requirements compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with Parts 38 and 39 of Article 49 of this Code and or the information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements set out in Parts 2 to 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation dated 29122004 190FZ
# 11170701764923
Unscheduled inspection
Start date: 2017-07-31, end date: 2017-08-11, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the implementation of the previously issued instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of a capital construction facility from 16062017 250316Uh171452 Verification by a legal entity of the elimination of violations specified in the instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of a capital construction facility from 16062017 250316UH171452PCOMPLIANCE by a legal entity of the instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of a capital construction facility from 16062017 250316Uh171452 P
# 11170701702456
Unscheduled inspection
Start date: 2017-06-13, end date: —, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 11170701698391
Unscheduled inspection
Start date: 2017-06-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 11170701652905
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 11170701614285
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 11170701614243
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-02, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the compliance of the completed works and the construction materials used at the capital construction facility "Construction and reconstruction of pipelines of the Pashninsky oil field, stage 5, stage 2, discharge line, well 3192 ZU 603", as well as the results of such work with the requirements of technical regulations, other regulations and project documentation Verification of the work performed in accordance with paragraph 1 of the Verification Program Verification of the legal entity's compliance with the requirements legislation on urban planning, environmental legislation, sanitary norms and rules, fire safety rules, industrial safety requirements, including requirements for energy efficiency and equipment of the capital construction facility "Construction and reconstruction of pipelines at the Pashninsky oil field, Stage 5, Stage 2, discharge line, well 3192 ZU 603" with metering devices for energy resources used, Compliance with the construction materials used during the construction of the capital construction facility as well as the results of the work performed to meet the requirements of the technical regulations of the project documentation, including energy efficiency requirements and equipment requirements for the capital construction facility "Construction and reconstruction of pipelines of the Pashninsky oil field, Stage 5, Stage 2, discharge line well 3192 ZU 603"Availability of a construction permit Compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation and compliance with regulations issued during the implementation of federal state construction supervision and construction control
# 11170701614176
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 11170701565117
Unscheduled inspection
Start date: 2017-04-24, end date: 2017-04-28, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of the audit is to verify the compliance of the completed works and the construction materials used at the capital construction facility "Construction and reconstruction of pipelines of the Pashninsky oil field Stage 5, stage 11 oil collector ZU 306 Node 4" as well as the results of such work with the requirements of technical regulations, other regulations and project documentation, Verification of the performance of work in accordance with paragraph 2 of the Inspection Program Verification tasks verification of compliance by a legal entity with the requirements of legislation on urban development, environmental legislation, sanitary norms and rules, fire safety regulations, industrial safety requirements, including energy efficiency requirements and equipment for the capital construction facility "Construction and reconstruction of pipelines at the Pashninsky oil field, Stage 5, Stage 11, oil collector ZU 306 Node 4" with metering devices for energy resources used to verify compliance with the applied construction materials during the construction of the capital construction facility, as well as the results of the work performed, meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility "Construction and reconstruction of pipelines of the Pashninsky oil field, Stage 5, stage 11 oil collector ZU 306 Node 4" with metering devices for used energy resources meeting the requirements of parts 2 and 3 of the article 52 of the Urban Planning Code of the Russian Federation
# 11170701565215
Unscheduled inspection
Start date: 2017-04-24, end date: 2017-04-28, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of the audit is to verify the compliance of the work performed and the construction materials used at the capital construction facility "Construction of high-pressure pipelines of the Pashninsky oil field, stage 2, stage 1 high-pressure water pipeline from BKNS to BNG4" as well as the results of such work with the requirements of technical regulations, other regulations and design documentation Verification of the work in accordance with paragraph 1 of the Inspection Program Verification tasks compliance by a legal entity with the requirements of legislation on urban development, environmental legislation, sanitary norms and rules, fire safety regulations, industrial safety requirements, including energy efficiency requirements and equipment for the capital construction facility "Construction of high-pressure pipelines at the Pashninsky oil field, Stage 2, Stage 1, high-pressure water pipeline from BKNS to BNG4" with metering devices for energy resources used to verify the compliance of building materials used in during the construction of the capital construction facility, as well as the results of the work performed, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility "Construction of high-pressure pipelines of the Pashninsky oil field, Stage 2, stage 1 high-pressure water pipeline from BKNS to BNG4" with metering devices for used energy resources, the availability of a construction permit, compliance with the requirements of parts 2 and 3 Article 52 of the Urban Planning Code of the Russian Federation