# 742005234973
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-11-27, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot po Uteplenie cherdaka Uteplenie polov tehetazha Montazh liftov Okrashivanie fasada Ustanovka okon Ustanovka mezhkomnatnyh dverei Ustanovka vhodnyh dverei Montazh vnutrennih setei vodoprovoda kanalizacii otopleniya Montazh ITP Vnutrennie elektromontazhnye raboty Montazh setei svyazi domofonnyh setei pozharnoi signalizacii Vnutrennie otdelochnye raboty Ustroistvo naruzhnogo vodoprovoda Ustroistvo naruzhnoi kanalizacii Ustroistvo naruzhnyh setei teplosnabzheniya Blagoustroistvo territorii Raboty po ozeleneniyu Ustanovka MAF v hode vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 nastoyaschego Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF
# 742005176362
Unscheduled inspection
Start date: 2020-10-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742004484286
Unscheduled inspection
Start date: 2020-08-24, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 742004484249
Unscheduled inspection
Start date: 2020-08-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 742004462283
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-07-31, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of PVC window blocks installation of internal water supply and sanitation networks installation of sanitary appliances installation of internal power supply networks installation of internal heating networks installation of communication networks and intercom system installation of elevator equipment, etc. installation of interior finishing works installation of wooden interior door blocks installation of metal entrance door blocks installation of external panel seams and facade painting installation on and used building materials in the process of construction reconstruction of a capital construction facility as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model if the formation and maintaining an information model is mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 742004449519
Unscheduled inspection
Start date: 2020-07-14, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 742004437205
Unscheduled inspection
Start date: 2020-06-25, end date: 2020-07-02, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 the work pemantau precast reinforced concrete 3-4 floors installation of precast reinforced concrete from 5 to 6 floors after completion of the installation of precast reinforced concrete on the 7th and 8th floors of the installation of precast reinforced concrete 9th-10th floor installation attic floor installation of the deflectors installation of metal structures assembling entrances installing window frames made of PVC installation of networks of water supply and sanitation installation of sanitary appliances installation power supply installation of the heating system, installation of communication networks and intercom system installation of Elevator equipment of the device interior decorating installing wooden interior doors external device interpanel seams and colouring of the facade installation of external networks radio and telephonization the process of work installation of external networks of water supply after the completion of installation of external networks of heating installation external Sewerage networks K1 installation of permanent power supply networks landscaping in the process of work and construction materials used in the process of construction, reconstruction of capital construction and the results of such work requirements approved in accordance with чч15 152 and 153 ст48 of Hardcodes project documentation given unit included in the project documentation in accordance with чч38 and 39 ст49 of Gradkowski and or informedly if the formation and maintenance of informedly are required in accordance with the requirements of Hardcodes to citrabuana of energeticamente except of capital construction on which energy performance requirements shall not apply and the requirements of the equipment object of capital construction of the metering devices of energy ресурсов2 have permission to строительство3 fulfillment of the requirements of CC 23 and 31 ст52 of the town planning code of the Russian Federation
# 742004423435
Unscheduled inspection
Start date: 2020-06-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741903079961
Unscheduled inspection
Start date: 2019-09-10, end date: 2019-09-16, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of work on the installation of precast reinforced concrete of 710 floors for the installation of entrance groups installation of PVC windows for the installation of internal and external engineering networks compliance with fire and sanitary epidemiological measures and building materials used during the construction of a capital construction facility as well as the results of such work with the requirements of design documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code Russian Federation
# 741902978633
Unscheduled inspection
Start date: 2019-08-27, end date: 2019-09-02, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of work on the installation of precast reinforced concrete of 46 floors for the installation of PVC windows for the installation of internal and external engineering networks and building materials used during the construction of a capital construction facility as well as the results of such work with the requirements of design documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation