# 422101331559
Unscheduled inspection
Start date: 2021-11-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422100899537
Unscheduled inspection
Start date: 2021-09-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422100822007
Unscheduled inspection
Start date: 2021-09-21, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives: to verify the compliance of the work performed and the construction materials and products used, as well as the results of such work, with the requirements of the design documentation (including taking into account the changes made to the working documentation and which, in accordance with Part 1.3 of Article 52 of the Civil Code of the Russian Federation, are part of such design documentation), during the construction of a capital construction facility. Tasks: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: compliance with the mandatory requirements of the legislation of the Russian Federation on urban development.
# 422100422661
Unscheduled inspection
Start date: 2021-08-16, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives: to verify the compliance of the work performed and the construction materials used in the production process with the requirements of the project documentation. Tasks: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development.
# 422100447761
Unscheduled inspection
Start date: 2021-08-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422100461028
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422100329574
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives: to verify the compliance of the work performed and the construction materials used in the production process with the requirements of the project documentation. Tasks: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development.
# 422100328335
Unscheduled inspection
Start date: 2021-07-08, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422100175164
Unscheduled inspection
Start date: 2021-04-30, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development
# 422100058697
Unscheduled inspection
Start date: 2021-03-25, end date: 2021-03-31, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Purpose: To verify the compliance of the work performed and the construction materials used in the course of work with the requirements of the project documentation. The purpose of this audit is to comply with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: Compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban development
# 422105344261
Unscheduled inspection
Start date: 2021-02-09, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection:
# 422100013340
Unscheduled inspection
Start date: 2021-02-16, end date: 2021-02-20, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives: to verify the compliance of the work performed and the construction materials used in the production process with the requirements of the project documentation. Tasks: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility. Subject: verification of compliance with the requirements of the legislation of the Russian Federation in the field of urban development.
# 422005259041
Unscheduled inspection
Start date: 2020-12-14, end date: 2020-12-18, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Celproverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverka vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa RF Zadacha soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva obekta Predmet soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti
# 422005259024
Unscheduled inspection
Start date: 2020-12-14, end date: 2020-12-18, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Celproverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverka vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa RF Zadacha soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva obekta Predmet soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti
# 422005259001
Unscheduled inspection
Start date: 2020-12-14, end date: 2020-12-18, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Celproverka sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverka vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa RF Zadacha soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva obekta Predmet soblyudenie trebovanii zakonodatelstva RF v oblasti gradostroitelnoi deyatelnosti
# 422005269130
Unscheduled inspection
Start date: 2020-12-11, end date: 2021-01-15, duration: 20
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: s celyu proverki sootvetstviya vypolnyaemyh rabot i primenennyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam v otnoshenii energeticheskoi effektivnosti i trebovaniyam v otnoshenii osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov zakonchennogo stroitelstvom obekta kapitalnogo stroitelstva zadachei i predmetom nastoyaschei proverki yavlyaetsya soblyudenie trebovanii zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti
# 422005178708
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-20, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: s celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta ustroistvo krovli vnutrennih sten i peregorodok polov fasada oshtukaturivanie kirpichnyh sten montazh vnutrennih inzhenernyh setei otoplenie vodosnabzhenie kanalizaciya elektrosnabzhenie ustanovka dverei vnutrennyaya otdelka MOP kvartir ustanovka oborudovaniya kvartir blagoustroistvo a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii zadachei i predmetom nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva
# 422004463559
Unscheduled inspection
Start date: 2020-07-21, end date: 2020-07-23, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: s celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kirpichnaya kladka sten montazh perekrytii ustroistvo krovli oshtukaturivanie kirpichnyh sten ustroistvo vnutrennih sten i peregorodok polov montazh vnutrennih inzhenernyh setei otoplenie vodosnabzhenie kanalizaciya elektrosnabzhenie okon ustroistvo fasada ustanovka dverei ustroistvo naruzhnyh setei blagoustroistvo territorii a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii zadachei i predmetom nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva
# 422004405131
Unscheduled inspection
Start date: 2020-05-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 422004369735
Unscheduled inspection
Start date: 2020-03-26, end date: 2020-03-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: s celyu proverki sootvetstviya vypolnyaemyh rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Mnogokvartirnyi zhiloi dom Kemerovskaya oblast Topkinskoe gorodskoe poselenie mkr Solnechnyi 14» raspolozhennogo po adresu Kemerovskaya oblast g Topki mkr Solnechnyi 14 a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii proverki vypolneniya trebovanii chastei 2 3 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii zadachei i predmetom nastoyaschei proverki yavlyaetsya soblyudenie zakonodatelstva Rossiiskoi Federacii o gradostroitelnoi deyatelnosti pri osuschestvlenii stroitelstva
# 421903449070
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-09-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902830852
Unscheduled inspection
Start date: 2019-07-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421902847458
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902830115
Unscheduled inspection
Start date: 2019-06-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421902685582
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-05-17, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902691112
Unscheduled inspection
Start date: 2019-05-27, end date: 2019-05-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902543355
Unscheduled inspection
Start date: 2019-03-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421902564876
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-03-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902600863
Unscheduled inspection
Start date: 2019-03-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 421902515170
Unscheduled inspection
Start date: 2019-02-11, end date: 2019-02-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902530961
Unscheduled inspection
Start date: 2019-02-22, end date: 2019-02-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902511010
Unscheduled inspection
Start date: 2019-02-06, end date: 2019-02-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421902507703
Unscheduled inspection
Start date: 2019-01-25, end date: 2019-01-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421802214874
Unscheduled inspection
Start date: 2018-12-12, end date: 2018-12-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421802214815
Unscheduled inspection
Start date: 2018-12-12, end date: 2018-12-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning
# 421802192090
Unscheduled inspection
Start date: 2018-12-12, end date: 2018-12-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kuzbassa
Purpose of inspection: Objectives verification of compliance of the work performed and the construction materials used in the course of work tasks compliance with the requirements of the legislation of the Russian Federation in the field of urban planning activities during the construction of a capital construction facility subject to compliance with the mandatory requirements of the legislation of the Russian Federation in the field of urban planning