# 742100345815
Unscheduled inspection
Start date: 2021-07-15, end date: 2021-07-21, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of works on landscaping and microrelief formation, landscaping, arrangement of entrances and porches, concrete blind areas along exterior walls, sidewalks and driveways made of double-layer asphalt concrete pavement, installation of underground and aboveground gas supply pipelines, installation of a boiler room, compliance with fire and sanitary and epidemiological measures and the construction materials used during the construction and reconstruction of a capital construction facility construction, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of information models are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping a capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 742100227274
Unscheduled inspection
Start date: 2021-05-25, end date: 2021-05-31, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the installation of internal engineering systems for heating, hot and cold water supply, electricity, sewerage, ventilation, installation of concrete floors, interior decoration of commercial and built-in premises of the 1st and 2nd floors and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work requirements the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Energy efficiency requirements (with the exception of capital construction facilities, to which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of art.52 of the Urban Planning Code of the Russian Federation.
# 742004457828
Unscheduled inspection
Start date: 2020-07-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74160700928909
Unscheduled inspection
Start date: 2016-10-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 74160601774354
Unscheduled inspection
Start date: 2016-08-24, end date: 2016-08-30, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the installation of concrete floors after the actual completion of work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74160601774305
Unscheduled inspection
Start date: 2016-08-11, end date: 2016-08-17, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of work on painting metal structures beams roof girders pipelines and fire protection of metal structures columns stairs after the actual completion of work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation2the need for a construction permit3compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation