# 772101291489
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100399313
Unscheduled inspection
Start date: 2021-07-30, end date: 2021-08-05, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of the fulfillment of the prescription; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the prescription issued by Mosgosstroynadzor compliance of the parameters of the capital construction facility with the maximum parameters of permitted construction, reconstruction of facilities capital construction, established by the rules of land use and development, documentation on the layout of the territory, and mandatory requirements for the parameters of capital construction facilities established by the Urban Planning Code and other federal laws
# 772100258379
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-25, duration: 14
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 771904190144
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used
# 771903625743
Unscheduled inspection
Start date: 2019-09-10, end date: 2019-09-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit is to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the audited person. The purpose of the audit is to verify the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and requirements for the equipment of the capital construction facility with metering devices for used energy resources
# 77190803484325
Unscheduled inspection
Start date: 2019-08-23, end date: 2019-08-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803440989
Unscheduled inspection
Start date: 2019-06-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803339639
Unscheduled inspection
Start date: 2019-02-19, end date: 2019-03-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803304514
Unscheduled inspection
Start date: 2018-12-20, end date: 2018-12-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803273406
Unscheduled inspection
Start date: 2018-11-12, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803217951
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803170783
Unscheduled inspection
Start date: 2018-06-28, end date: 2018-07-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used