# 262005234470
Unscheduled inspection
Start date: 2020-11-19, end date: 2020-12-16, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: inspection program from 17042020 10012020 stage 2 3 4 prevention identification and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out construction, compliance with the procedure for conducting construction control, maintaining general and or special work logs, executive documentation, and drawing up certificates of work inspection of structures, sections of engineering and technical support networks, compliance with other requirements when performance of works established by the project documentation, including requirements regarding energy efficiency and requirements regarding the equipment of the capital construction facility with metering devices for the energy resources used, compliance with mandatory requirements and or requirements established by municipal legal acts
# 262005172761
Unscheduled inspection
Start date: 2020-10-07, end date: 2020-11-03, duration: —
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: inspection program 32072020 from 20082020 identification and suppression of violations of the legislation on urban planning activities committed by the developer, the technical customer, and the person carrying out construction, including technical regulations and project documentation, compliance with the procedure for conducting construction control, maintaining general and or special logs of work, executive documentation, and drawing up certificates of inspection of structures, sections of engineering support networks, and compliance with other requirements when performing work established by the project documentation including requirements regarding energy efficiency and requirements regarding the equipment of a capital construction facility with metering devices for used energy resources compliance with mandatory requirements and or requirements established by municipal legal acts
# 262005186770
Unscheduled inspection
Start date: 2020-10-15, end date: 2020-11-12, duration: 20
Authority: Ministerstvo stroitelstva i arhitektury Stavropolskogo kraya
Purpose of inspection: inspection program from 17042020 10012020 stage 2 prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, and the person carrying out construction, compliance with the procedure for conducting construction control, maintaining general and or special work logs, executive documentation, and drawing up certificates of work inspection of structures, sections of engineering support networks
# 262004494788
Unscheduled inspection
Start date: 2020-08-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 261903889129
Unscheduled inspection
Start date: 2019-10-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 261802052862
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-12-03, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: This audit is conducted for the purpose of notification dated 25102018 498 of SMDS PMK LLC on the completion dates of the works that are subject to verification inspection program 29042018 dated 06082018 the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction. The subject of this audit is compliance with the procedure carrying out construction control maintaining general and or special work logs of executive documentation drawing up certificates of inspection of structures of sections of engineering and technical support networks compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping the capital construction facility with metering devices for energy resources used
# 261801686947
Unscheduled inspection
Start date: 2018-09-25, end date: 2018-10-22, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: notice dated 20092018 148910114 to the administration of the Izobilnensky City District of the Stavropol Territory on the completion of construction FINAL INSPECTION the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer, technical customer, and person carrying out construction, including technical regulations and project documentation, compliance with the procedure for conducting construction control, maintaining general and or special work logs, executive documentation, and drawing up inspection reports compliance with other requirements when performing work established by the design documentation, including requirements regarding energy efficiency and requirements regarding the equipment of the capital construction facility with metering devices for used energy resources compliance with mandatory requirements and or requirements established by municipal legal acts
# 261800586949
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-24, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: notice dated 24072018 0536452 to the administration of the Izobilnensky city District of the Stavropol Territory notice of completion of construction FINAL INSPECTION inspection program 32102016 dated 24062016 the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer technical customer person carrying out construction, including technical regulations and project documentation the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 261800492379
Unscheduled inspection
Start date: 2018-06-26, end date: 2018-07-23, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: notice dated 15062018 0535139 to the administration of the Izobilnensky city District of the Stavropol Territory notice of completion of construction FINAL INSPECTION inspection program 32102016 dated 24062016 the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer technical customer person carrying out construction, including technical regulations and project documentation The subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts
# 261800009898
Unscheduled inspection
Start date: 2018-01-29, end date: 2018-02-26, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: this inspection is conducted for the purpose of notification dated 25/122017 5541 to the administration of the city of Izobilny in the Izobilnensky district of the Stavropol Territory on the deadlines for completion of works that are subject to verification inspection program 32102016 dated 24062016 the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer technical customer person carrying out construction, including technical regulations and project documentation the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal legal acts