# 472004423608
Unscheduled inspection
Start date: 2020-06-03, end date: 2020-07-01, duration: 4
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 471902920750
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 471902712062
Unscheduled inspection
Start date: 2019-05-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471802173116
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-12-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of the audit is to verify the application of citizens, including individual entrepreneurs, legal entities, information from public authorities, officials of the state supervisory authority, local governments, and the media. The subject of this audit is compliance with mandatory requirements, including compliance with the performance of work and the construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work with technical requirements. regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 781802073048
Unscheduled inspection
Start date: 2018-10-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471800502284
Unscheduled inspection
Start date: 2018-06-22, end date: 2018-07-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 47170701434520
Unscheduled inspection
Start date: 2017-03-06, end date: 2017-04-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this check is compliance with mandatory requirements including compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation