Found 4 inspections:

# 272101430010
Unscheduled inspection
Start date: 2021-12-06, end date: —, duration:
Authority:
Purpose of inspection:


# 272100446699
Unscheduled inspection
Start date: 2021-08-09, end date: —, duration:
Authority:
Purpose of inspection:


# 272000126949
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-30, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program dated 08/12/2020. The objectives of this audit are: prevention, detection, suppression of violations of current legislation on urban development, including project documentation. The subject of the audit is to verify the compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements (with the exception of capital construction facilities, to which energy efficiency requirements do not apply) and the requirements of equipping the capital construction facility with metering devices for the energy used resources.


# 272005243038
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora Pravitelstva Habarovskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision on the basis of the inspection program from 12082020 The objectives of this inspection are to prevent identify and suppress violations of current legislation on urban development activities, including design documentationthe subject of the inspection is to verify the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements project documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.