Found 5 inspections:

# 001902712472
Unscheduled inspection
Start date: 2019-05-15, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection:


# 001902432127
Unscheduled inspection
Start date: 2019-01-15, end date: —, duration:
Authority:
Purpose of inspection:


# 001902816985
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-03, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the fulfillment of the previously issued regulation dated 24052019 10904 deadline 19062019 The objectives of this audit are 1 to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation 2 to prevent identify and suppress violations of legislation on urban development committed by the developer the customer as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including technical regulations and project documentation The subject of this audit is the fulfillment of the instruction issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region


# 001902712472
Unscheduled inspection
Start date: 2019-05-15, end date: 2019-05-24, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the fulfillment of the previously issued regulation dated 17042019 15674 deadline 300-42019 The objectives of this audit are 1 to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation 2 to prevent identify and suppress violations of legislation on urban development committed by the developer the customer as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including technical regulations and project documentation The subject of this audit is the fulfillment of the instruction issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region


# 001902432127
Unscheduled inspection
Start date: 2019-01-15, end date: 2019-01-24, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Novosibirskoi oblasti
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued regulation dated 25092018 182285 due date 25112018 The objectives of this inspection are 1 to verify the elimination of violations and compliance with the requirements of the measures specified in the regulation 2 to prevent identify and suppress violations of legislation on urban development committed by the developer the customer as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including technical regulations and project documentation The subject of this audit is the fulfillment of the instruction issued by the Inspectorate of the State Construction Supervision of the Novosibirsk region


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.