# 342101532977
Unscheduled inspection
Start date: 2021-12-23, end date: 2021-12-27, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: This inspection is carried out in accordance with the inspection program received by a representative of the technical customer, LLC PSO Volgograd, in order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation and project documentation. The purpose of this inspection is to prevent, identify and suppress violations of the legislation of the Russian Federation and project documentation, the subject of this inspection is compliance with mandatory requirements regarding: a) the conformity of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter referred to as the Code) (including changes made to the working documentation and which are part of such project documentation in accordance with Part 1.3 of Article 52 of the Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Code) b) requirements for a construction permit; c) requirements established by parts 2 and 3.1 of Article 52 of the Code; d) requirements established by part 4 of Article 52 of the Code to ensure the conservation of a capital construction facility; e) requirements for the procedure for carrying out construction control established by the Code and other regulatory legal acts.
# 342101204544
Unscheduled inspection
Start date: 2021-10-19, end date: 2021-10-21, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The inspection is carried out in accordance with the inspection program received by a representative of the technical customer, LLC PSO Volgograd, in order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation and project documentation. The purpose of this inspection is to prevent, identify and suppress violations of the legislation of the Russian Federation and project documentation. The subject of this inspection is compliance with mandatory requirements regarding: a) the conformity of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (hereinafter referred to as the Code) (including changes made to the working documentation and which are part of such project documentation in accordance with Part 1.3 of Article 52 of the Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Code) b) requirements for a construction permit; c) requirements established by parts 2 and 3.1 of Article 52 of the Code; d) requirements established by part 4 of Article 52 of the Code to ensure the conservation of a capital construction facility; e) requirements for the procedure for carrying out construction control established by the Code and other regulatory legal acts
# 342100475089
Unscheduled inspection
Start date: 2021-08-13, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 342100321036
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: in order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources, including technical regulations and design documentation;
The purpose of this audit is to prevent, identify and suppress violations of the legislation of the Russian Federation, including technical regulations, and project documentation. The subject of this audit is compliance with mandatory requirements
# 342005284599
Unscheduled inspection
Start date: 2020-12-21, end date: 2020-12-25, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: verification is done with the purpose of conformity assessment activities undertaken at the Facility requirements of planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection requirements of fire safety and sanitary and epidemiological welfare of the population as well as the requirements of the energy efficiency requirements of equipment of a capital construction object metering devices of energy resources including technical regulations and project documentation b the purpose of this check is to prevent the detection and suppression of violations of laws of the Russian Federation including technical regulations and project documentation 7 the Subject of this review is to comply with the mandatory requirements and the compliance of contractors and construction materials used in the construction process of the reconstruction of the object of capital the construction and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code further, the Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources b the availability of building permits in compliance established in parts 2 and 3 of article 31 of 52 of the town planning code of the Russian Federation
# 341902519283
Unscheduled inspection
Start date: 2019-03-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 34170701482695
Unscheduled inspection
Start date: 2017-03-29, end date: 2017-03-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: assessment of compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population, including technical regulations and project documentationthe purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentationthe subject of this audit is compliance with mandatory requirements in relation to the compliance of construction works with their results and the construction materials used with the requirements of the technical regulations of the project documentation and the fulfillment of the established requirements for admission to construction work
# 34160701031400
Unscheduled inspection
Start date: 2016-10-20, end date: —, duration: —
Authority: —
Purpose of inspection: