# 772004476971
Unscheduled inspection
Start date: 2020-08-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004506549
Unscheduled inspection
Start date: 2020-08-24, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004445488
Unscheduled inspection
Start date: 2020-07-03, end date: 2020-07-30, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notice from the developer of the customer. The objectives of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activities by the person being audited. The subject of the audit is to verify the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources
# 772004309705
Unscheduled inspection
Start date: 2020-02-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004220289
Unscheduled inspection
Start date: 2020-01-23, end date: 2020-02-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 771904056712
Unscheduled inspection
Start date: 2019-12-03, end date: 2019-12-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 771903993520
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-11-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify compliance with the instructions of the Moscow State Construction Supervision
# 771903907324
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-10-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used