Found 11 inspections:

# 002005234186
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-11, duration: 15
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this check is carried out in order to control the execution by a legal entity of a previously issued prescription. The task of this check is to eliminate the facts of compliance with the previously issued prescription. The subject of this check is the execution of an instruction to eliminate identified violations


# 002004217767
Unscheduled inspection
Start date: 2020-01-21, end date: —, duration:
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 002005234186
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-11, duration: 15
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this check is carried out in order to control the execution by a legal entity of a previously issued prescription. The task of this check is to eliminate the facts of compliance with the previously issued prescription. The subject of this check is the execution of an instruction to eliminate identified violations


# 002004217767
Unscheduled inspection
Start date: 2020-01-21, end date: 2020-01-27, duration:
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution by a legal entity of a previously issued prescription The task of this audit is to establish the facts of the fulfillment of the above-mentioned prescription by Gazstroyengineering LLC. The subject of this audit is the execution by Gazstroyengineering LLC of the Prescription for the elimination of identified violations


# 34170701891565
Unscheduled inspection
Start date: 2017-08-15, end date: —, duration:
Authority:
Purpose of inspection:


# 34170701729184
Unscheduled inspection
Start date: 2017-06-23, end date: —, duration:
Authority:
Purpose of inspection:


# 34170701718518
Unscheduled inspection
Start date: 2017-06-23, end date: 2017-07-03, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation The task is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation The subject is compliance with mandatory requirements with regard to a the compliance of construction works with their results and the construction materials used with the requirements of technical regulations of project documentation b the availability of a construction permit c compliance with the established requirements for admission to construction work


# 34170701618107
Unscheduled inspection
Start date: 2017-05-19, end date: 2017-05-29, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation The task is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentation The subject is compliance with mandatory requirements with regard to a the compliance of construction works with their results and the construction materials used with the requirements of technical regulations of project documentation b the availability of a construction permit c compliance with the established requirements for admission to construction work


# 34170701562722
Unscheduled inspection
Start date: 2017-04-25, end date: —, duration:
Authority:
Purpose of inspection:


# 34160701011944
Unscheduled inspection
Start date: 2016-10-14, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:


# 34160601703897
Unscheduled inspection
Start date: 2016-07-13, end date: 2016-07-21, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: assessment of compliance of activities carried out at the facility with the requirements of urban planning legislation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.