# 282101425673
Unscheduled inspection
Start date: 2021-12-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 282100786450
Unscheduled inspection
Start date: 2021-09-20, end date: 2021-10-01, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: - execution of the inspection program, prevention, identification and suppression of violations committed by the developer, the technical customer, the person carrying out construction of compliance with the requirements of the project documentation performed during the construction of the capital construction facility, as well as the results of such work, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources., verification compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.
# 282100340587
Unscheduled inspection
Start date: 2021-07-09, end date: 2021-07-23, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: execution of the inspection program, prevention, detection and suppression of violations committed by the developer, the technical customer, the person carrying out the construction of violations of compliance performed during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used., verification of compliance with the implementation works and construction materials used during the construction of a capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used.
# 281903928776
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-12-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to implement the inspection program from 16052019the tasks of this inspection are to prevent identify and suppress violations committed by the developer, the technical customer, the person carrying out the construction of compliance with the requirements of the project documentation performed during the construction of the capital construction facility, as well as the results of such work, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for the energy used The subject of this audit is to verify the compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 281903594108
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-10-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The tasks of this audit are the prevention detection and suppression of violations committed by the developer, the technical customer, the person carrying out the construction of violations of compliance performed during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources7 The subject of this audit is the verification of compliance the performance of works and construction materials used in the construction of a capital construction facility as well as the results of such work to the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 281902903197
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The tasks of this audit are the prevention detection and suppression of violations committed by the developer, the technical customer, the person carrying out the construction of violations of compliance performed during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources7 The subject of this audit is the verification of compliance the performance of works and construction materials used in the construction of a capital construction facility as well as the results of such work to the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 281902762724
Unscheduled inspection
Start date: 2019-06-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 281902727090
Unscheduled inspection
Start date: 2019-05-28, end date: 2019-06-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Amurskoi oblasti
Purpose of inspection: The tasks of this audit are the prevention detection and suppression of violations committed by the developer, the technical customer, the person carrying out the construction of violations of compliance performed during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources7 The subject of this audit is the verification of compliance the performance of works and construction materials used in the construction of a capital construction facility as well as the results of such work to the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used