# 772101433251
Unscheduled inspection
Start date: 2021-12-08, end date: 2021-12-09, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772101432938
Unscheduled inspection
Start date: 2021-12-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101494365
Unscheduled inspection
Start date: 2021-12-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101493787
Unscheduled inspection
Start date: 2021-12-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101474591
Unscheduled inspection
Start date: 2021-12-17, end date: 2021-12-30, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772101455351
Unscheduled inspection
Start date: 2021-12-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101260631
Unscheduled inspection
Start date: 2021-11-10, end date: 2021-11-19, duration: 8
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772101386869
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101385305
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101391825
Unscheduled inspection
Start date: 2021-11-29, end date: 2021-12-10, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772101390484
Unscheduled inspection
Start date: 2021-11-29, end date: 2021-12-03, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772101305718
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101390812
Unscheduled inspection
Start date: 2021-11-25, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772101376286
Unscheduled inspection
Start date: 2021-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101359975
Unscheduled inspection
Start date: 2021-11-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101334345
Unscheduled inspection
Start date: 2021-11-16, end date: 2021-11-22, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772101155822
Unscheduled inspection
Start date: 2021-10-06, end date: 2021-10-22, duration: 13
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772101248572
Unscheduled inspection
Start date: 2021-10-22, end date: 2021-11-10, duration: 12
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100643177
Unscheduled inspection
Start date: 2021-09-08, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100643179
Unscheduled inspection
Start date: 2021-09-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101051451
Unscheduled inspection
Start date: 2021-09-29, end date: 2021-09-30, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100895102
Unscheduled inspection
Start date: 2021-09-24, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100456715
Unscheduled inspection
Start date: 2021-08-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100472992
Unscheduled inspection
Start date: 2021-08-13, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100349377
Unscheduled inspection
Start date: 2021-07-15, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100358694
Unscheduled inspection
Start date: 2021-07-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100347594
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100397306
Unscheduled inspection
Start date: 2021-07-30, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100295152
Unscheduled inspection
Start date: 2021-06-18, end date: 2021-07-01, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100298774
Unscheduled inspection
Start date: 2021-06-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100293372
Unscheduled inspection
Start date: 2021-06-21, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100220585
Unscheduled inspection
Start date: 2021-05-18, end date: 2021-05-31, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100212606
Unscheduled inspection
Start date: 2021-05-31, end date: 2021-06-08, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100212888
Unscheduled inspection
Start date: 2021-05-31, end date: 2021-06-08, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100212444
Unscheduled inspection
Start date: 2021-05-31, end date: 2021-06-08, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100212309
Unscheduled inspection
Start date: 2021-05-31, end date: 2021-06-08, duration: 7
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100212980
Unscheduled inspection
Start date: 2021-05-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100247301
Unscheduled inspection
Start date: 2021-05-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100177256
Unscheduled inspection
Start date: 2021-04-27, end date: 2021-05-26, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100177255
Unscheduled inspection
Start date: 2021-04-27, end date: 2021-05-26, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100181831
Unscheduled inspection
Start date: 2021-04-27, end date: 2021-05-20, duration: 16
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100063310
Unscheduled inspection
Start date: 2021-03-22, end date: 2021-04-09, duration: 15
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772005252959
Unscheduled inspection
Start date: 2020-12-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772005202358
Unscheduled inspection
Start date: 2020-10-23, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772005172784
Unscheduled inspection
Start date: 2020-10-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004481589
Unscheduled inspection
Start date: 2020-08-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004510410
Unscheduled inspection
Start date: 2020-08-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004479390
Unscheduled inspection
Start date: 2020-08-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004486842
Unscheduled inspection
Start date: 2020-08-13, end date: 2020-09-09, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notice from the developer of the customer. The objectives of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activities by the person being audited. The subject of the audit is to verify the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources
# 772004486610
Unscheduled inspection
Start date: 2020-08-13, end date: 2020-09-09, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notice from the developer of the customer. The objectives of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activities by the person being audited. The subject of the audit is to verify the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources
# 772004466221
Unscheduled inspection
Start date: 2020-07-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004445527
Unscheduled inspection
Start date: 2020-07-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004463215
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004461310
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004460478
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004439538
Unscheduled inspection
Start date: 2020-06-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004420159
Unscheduled inspection
Start date: 2020-05-27, end date: 2020-06-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 772004337495
Unscheduled inspection
Start date: 2020-03-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004337674
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-03-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772004374896
Unscheduled inspection
Start date: 2020-03-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004385553
Unscheduled inspection
Start date: 2020-03-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004370295
Unscheduled inspection
Start date: 2020-03-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004353162
Unscheduled inspection
Start date: 2020-03-12, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004291094
Unscheduled inspection
Start date: 2020-02-12, end date: 2020-02-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 772004287763
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-03-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 772004287860
Unscheduled inspection
Start date: 2020-02-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004167962
Unscheduled inspection
Start date: 2020-01-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004240378
Unscheduled inspection
Start date: 2020-01-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004248098
Unscheduled inspection
Start date: 2020-01-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004216411
Unscheduled inspection
Start date: 2020-01-20, end date: 2020-01-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771904154454
Unscheduled inspection
Start date: 2019-12-25, end date: 2020-01-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used
# 771904148945
Unscheduled inspection
Start date: 2019-12-25, end date: 2020-01-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for energy resources used
# 771904058396
Unscheduled inspection
Start date: 2019-12-05, end date: 2019-12-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for energy resources used
# 771904071089
Unscheduled inspection
Start date: 2019-12-06, end date: 2019-12-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used
# 771904089466
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used
# 771904085836
Unscheduled inspection
Start date: 2019-12-12, end date: 2019-12-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771904030850
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-11-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 771903834961
Unscheduled inspection
Start date: 2019-10-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903800604
Unscheduled inspection
Start date: 2019-10-08, end date: 2019-10-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit is to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the audited person. The purpose of the audit is to verify the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and requirements for the equipment of the capital construction facility with metering devices for used energy resources
# 771903870670
Unscheduled inspection
Start date: 2019-10-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903506489
Unscheduled inspection
Start date: 2019-09-05, end date: 2019-09-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803472820
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803484328
Unscheduled inspection
Start date: 2019-08-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803481744
Unscheduled inspection
Start date: 2019-08-21, end date: 2019-08-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803471174
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803458509
Unscheduled inspection
Start date: 2019-07-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803460362
Unscheduled inspection
Start date: 2019-07-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803448605
Unscheduled inspection
Start date: 2019-07-01, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77190803447765
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803464612
Unscheduled inspection
Start date: 2019-07-24, end date: 2019-07-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the receipt of a notice from the developer to the customer, preventing the identification and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the person being audited. compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for used energy resources
# 77190803422146
Unscheduled inspection
Start date: 2019-06-18, end date: 2019-06-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803443001
Unscheduled inspection
Start date: 2019-06-19, end date: 2019-06-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803440776
Unscheduled inspection
Start date: 2019-06-19, end date: 2019-06-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803441634
Unscheduled inspection
Start date: 2019-06-20, end date: 2019-06-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: This inspection is carried out in order to carry out control measures in connection with the receipt of a notification from the client's developer or the person carrying out the construction on the start of work, which provides for state construction supervision from 06062019 09 and 2401900the objectives of this inspection are to prevent identify and suppress violations of the requirements of the design documentation legislation on urban development activities by the person being audited. The subject of this inspection is the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.
# 771902823186
Unscheduled inspection
Start date: 2019-06-21, end date: 2019-07-18, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control of a previously issued prescription
# 77190803443973
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803447702
Unscheduled inspection
Start date: 2019-06-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77190803417583
Unscheduled inspection
Start date: 2019-05-23, end date: 2019-06-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771902710486
Unscheduled inspection
Start date: 2019-05-08, end date: 2019-06-06, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: The audit is conducted in order to protect the rights and interests of employees in connection with the receipt by the Inspectorate of an employee's application 7771004919. The objectives of the audit are supervision and control over compliance with legislation and other regulatory legal acts containing labor law norms. The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts. compliance with information contained in the notification of the commencement of certain types of activities compliance of information contained in the application and documents of a legal entity or individual entrepreneur on granting the legal status of a special permit license permit approval with mandatory requirements as well as data on these legal entities and individual entrepreneurs contained in the unified state register of individual entrepreneurs and other federal information resources compliance with the instructions of state control bodies supervision bodies of municipal control conducting measures to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites, historical and cultural monuments of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, documents of special historical significance, scientific and cultural significance included in the national library fund for the prevention of natural and man-made emergencies, State security measures to eliminate the consequences of causing such harm
# 77190803409796
Unscheduled inspection
Start date: 2019-05-08, end date: 2019-05-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: This inspection is carried out in order to carry out control measures in connection with the receipt of a notification from the client's developer or the person carrying out construction on the start of work, which provides for state construction supervision from 15042019 09 and 1681900. The objectives of this inspection are to prevent identify and suppress violations of the requirements of the design documentation of legislation on urban development activities by the person being audited. The verification is the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used.
# 77190803409168
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803401996
Unscheduled inspection
Start date: 2019-04-19, end date: 2019-05-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803390646
Unscheduled inspection
Start date: 2019-04-08, end date: 2019-04-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771902445138
Unscheduled inspection
Start date: 2019-01-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771802191594
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-28, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control of the execution of the previously issued instruction on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protective facilities and to prevent the threat of fire 4281114 dated December 22, 2017
# 771802222409
Unscheduled inspection
Start date: 2018-12-10, end date: 2019-01-14, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control over the implementation of the GPN regulation dated 22032018 428111 on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protection facilities and to prevent the threat of fire
# 77180803274335
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-11-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803273320
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-11-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771801512979
Unscheduled inspection
Start date: 2018-09-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803232973
Unscheduled inspection
Start date: 2018-09-24, end date: 2018-09-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803232974
Unscheduled inspection
Start date: 2018-09-24, end date: 2018-09-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803237558
Unscheduled inspection
Start date: 2018-09-25, end date: 2018-09-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803235883
Unscheduled inspection
Start date: 2018-09-25, end date: 2018-09-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771801647433
Unscheduled inspection
Start date: 2018-08-15, end date: 2018-09-11, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: monitoring the implementation of the instruction to eliminate violations of mandatory fire safety requirements dated September 11, 2017 18411, the deadline for which has expired, in accordance with the procedure established by the legislation of the Russian Federation, checking compliance with fire safety requirements at the protection facility established by federal laws and other regulatory legal acts of the Russian Federation adopted in accordance with them and taking measures based on the results of the audit compliance with the regulations of state control bodies, supervision bodies of municipal control
# 771800602376
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-31, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control over the execution of the instruction of the 2nd regional Department of Supervision and Preventive Work of the Main Directorate of the Ministry of Emergency Situations of Russia in Moscow 1111 dated 21022/2018 on the elimination of violations of fire safety requirements on carrying out measures to ensure fire safety at the protection facility and to prevent the threat of fire
# 77180803197536
Unscheduled inspection
Start date: 2018-08-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803212339
Unscheduled inspection
Start date: 2018-08-23, end date: 2018-08-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771800313827
Unscheduled inspection
Start date: 2018-04-18, end date: 2018-05-14, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: To establish that this inspection is carried out in order to monitor compliance with fire safety requirements in accordance with the instructions of the Deputy Minister of the Ministry of Emergency Situations of Russia SA Kadadov dated 310318 91135019 of the Government of the Russian Federation dated 28032018 DMP41776 The objectives of this inspection are to carry out, in accordance with the procedure established by the legislation of the Russian Federation, verification of compliance with fire safety requirements at the protection facility established by federal laws and adopted in accordance with compliance with other regulatory legal acts of the Russian Federation and the adoption of measures based on the results of the audit The subject of this audit is compliance with mandatory requirements
# 771800283907
Unscheduled inspection
Start date: 2018-04-10, end date: 2018-05-10, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: The purpose of the audit is to monitor the execution of the instruction on the elimination of violations of fire safety requirements. The objectives of the audit are to carry out activities in accordance with the procedure established by the legislation of the Russian Federation to verify compliance by legal entities and individual entrepreneurs with mandatory fire safety requirements and to take measures based on the results of this audit. The subject of the audit is to comply with the instructions of state control bodies, supervision of municipal control bodies
# 771800278346
Unscheduled inspection
Start date: 2018-04-10, end date: 2018-05-10, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: execution of the order of the Deputy Minister of the Ministry of Emergency Situations of Russia dated 31032018 91135019 issued in accordance with the Government's instruction dated 28032018 471132018
# 771800279157
Unscheduled inspection
Start date: 2018-04-12, end date: 2018-05-11, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: Carrying out, in accordance with the procedure established by the legislation of the Russian Federation, verification of compliance with fire safety requirements at protection facilities established by federal laws and other regulatory legal acts of the Russian Federation adopted in accordance with them and taking measures based on the results of the audit
# 771800334660
Unscheduled inspection
Start date: 2018-04-17, end date: 2018-05-14, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: fire supervision 69FZ compliance with fire safety requirements For the execution of the order of the Government of the Russian Federation dated March 28, 2018 DMP41776 instructions of the First Deputy Prosecutor General of the Russian Federation AE Buksmann dated March 26, 2018 471132018
# 77180803080746
Unscheduled inspection
Start date: 2018-02-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803076881
Unscheduled inspection
Start date: 2018-02-12, end date: 2018-02-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 771800077502
Unscheduled inspection
Start date: 2018-01-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802961136
Unscheduled inspection
Start date: 2017-12-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802827291
Unscheduled inspection
Start date: 2017-11-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802078205
Unscheduled inspection
Start date: 2017-09-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802522419
Unscheduled inspection
Start date: 2017-09-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701903569
Unscheduled inspection
Start date: 2017-08-21, end date: —, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection:
# 77170701677088
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-07-10, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control over the implementation of the GPN 64811 regulation on the elimination of violations of mandatory fire safety requirements
# 77170701675240
Unscheduled inspection
Start date: 2017-06-02, end date: 2017-06-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701593981
Unscheduled inspection
Start date: 2017-05-02, end date: —, duration: —
Authority: —
Purpose of inspection: