# 162004403678
Unscheduled inspection
Start date: 2020-05-07, end date: 2020-05-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 28022020 case 190420190026 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004323438
Unscheduled inspection
Start date: 2020-03-17, end date: 2020-03-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu opredeleniya sootvetstviya ustranennyh narushenii trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii drugih normativnyh aktov norm i pravil opredeleniya fakta ispolneniya predpisaniya a takzhe s celyu sostavleniya akta ob ustranenii narushenii ispolneniya predpisaniya na osnovanii postupivshego v Inspekciyu izvescheniya ot 26022020 1975 ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva kotorye bylo predpisano ustranit v srok ustanovlennyi predpisaniem ot 10022020 1912000801 do 16032020 i istecheniya sroka ispolneniya predpisaniya ot 10022020 1912000801 srok ispolneniya kotorogo istek 16032020 Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora organov municipalnogo kontrolya
# 162004303039
Unscheduled inspection
Start date: 2020-02-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004222720
Unscheduled inspection
Start date: 2020-01-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161904089868
Unscheduled inspection
Start date: 2019-12-12, end date: 2019-12-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the construction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 03072019 case 190420190026the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903937572
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-25, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 03072019 case 190420190026the tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by municipal authorities legal acts
# 161903620923
Unscheduled inspection
Start date: 2019-09-26, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: