Found 9 inspections:

# 492100280478
Unscheduled inspection
Start date: 2021-06-10, end date: —, duration: 11
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Control of the compliance of completed works with the mandatory requirements of technical regulations, other regulatory legal acts, project documentation, requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the notice of completion of construction dated 06/04/2021 No. 7. 2. Prevention, detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of the Sopka Quartz and Dalnoye deposits" committed by the developer, technical customer, and persons engaged in construction on the basis of a contract with the developer or technical customer and "Oroch". The leaching section." 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100280336
Unscheduled inspection
Start date: 2021-06-10, end date: —, duration: 11
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Implementation of the inspection program dated 12/28/2020 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of the Sopka Quartz and Dalnoye deposits" committed by the developer, technical customer, and persons engaged in construction on the basis of a contract with the developer or technical customer and "Oroch". Boiler room". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100280431
Unscheduled inspection
Start date: 2021-06-10, end date: —, duration: 11
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/28/2020 for the implementation of state construction supervision over the construction of the capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of the Sopka Quartz and Dalnoye deposits" committed by the developer, technical customer, and persons carrying out construction on the basis of a contract with the developer or technical customer and "Oroch". The building of hydrometallurgy". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100280398
Unscheduled inspection
Start date: 2021-06-10, end date: —, duration: 11
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Execution of the inspection program dated 12/28/2020 for the implementation of state construction supervision over the construction of a capital construction facility of the North-Eastern Directorate of Rostechnadzor for 2021. 2. Prevention, identification and suppression of violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of the Sopka Quartz and Dalnoye deposits" committed by the developer, technical customer, and persons engaged in construction on the basis of a contract with the developer or technical customer and "Oroch". Production laboratory". 3. Compliance of the work performed and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, design documentation, including energy efficiency requirements, and the requirements for equipping the capital construction facility with metering devices for energy resources used.;


# 492100280309
Unscheduled inspection
Start date: 2021-06-10, end date: —, duration: 11
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Control of compliance of completed works with the mandatory requirements of technical regulations, other regulatory legal acts, project documentation, requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the notice of completion of construction dated 06/04/2021 No. 6. 2. Prevention, identification and suppression of violations committed by the developer, the technical customer, as well as persons carrying out construction on the basis of a contract with a developer or a technical customer, violations of legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of the Sopka Quartz, Dalnoye and Oroch deposits". Energy Complex". 3. Compliance of the work performed and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, design documentation, including energy efficiency requirements, requirements for equipping the capital construction facility with metering devices for energy resources used;


# 492100157307
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-04-16, duration: 3
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This unscheduled documentary check is carried out in order to monitor the implementation of the previously issued regulation No. 05/802-2021 dated 12.02.2021. The purpose of this audit is to prevent, identify and suppress violations of legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of Sopka Quartz deposits", committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer.Distant" and "Oroch". A checkpoint." The subject of the audit is compliance with the regulations of state control (supervision) bodies and municipal control bodies.


# 492100157280
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-04-16, duration: 3
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This unscheduled documentary check is carried out in order to monitor the implementation of the previously issued regulation No. 05/804-2021 dated 12.02.2021. The purpose of this audit is to prevent, identify and suppress violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of Sopka Quartz deposits" committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer. "Distant" and "Oroch". Operator's office". The subject of the audit is compliance with the regulations of state control (supervision) bodies and municipal control bodies.


# 492100157294
Unscheduled inspection
Start date: 2021-04-14, end date: 2021-04-16, duration: 3
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This unscheduled documentary check is carried out in order to monitor the implementation of the previously issued regulation No. 05/805-2021 dated 12.02.2021. The purpose of this audit is to prevent, identify and suppress violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of Sopka Quartz deposits", committed by the developer, the technical customer, as well as by persons carrying out construction on the basis of a contract with the developer or the technical customer. "Distant" and "Oroch". Heating point". The subject of the audit is compliance with the regulations of state control (supervision) bodies and municipal control bodies.


# 492100075776
Unscheduled inspection
Start date: 2021-03-16, end date: 2021-03-18, duration: 2
Authority: Severo-Vostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: 1. Control over the execution of the previously issued regulation No. 05/803-2021 dated 12.02.2021. 2. Prevention, detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation during the construction of the capital construction facility "Processing of poor ores of the Sopka Quartz and Dalnoye deposits" committed by the developer, technical customer, and persons carrying out construction on the basis of a contract with the developer or technical customer and "Oroch". Container storage area for reagents". 3. Compliance with the regulations of state control (supervision) bodies and municipal control bodies.


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.