# 772101228480
Unscheduled inspection
Start date: 2021-10-20, end date: 2021-10-29, duration: 8
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the order issued by Mosgosstroynadzor
# 772100561219
Unscheduled inspection
Start date: 2021-09-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100387612
Unscheduled inspection
Start date: 2021-07-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100229749
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100110157
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-30, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772100094752
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-02, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772004446183
Unscheduled inspection
Start date: 2020-07-06, end date: 2020-07-17, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the audit program The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and requirements for the equipment of the capital construction facility with metering devices for used energy resources