# 001904157675
Unscheduled inspection
Start date: 2019-12-16, end date: 2019-12-19, duration: —
Authority: Komitet ohotnichego hozyaistva i rybolovstva Saratovskoi oblasti
Purpose of inspection: Execution of a previously issued prescription
# 001801460758
Unscheduled inspection
Start date: 2018-09-20, end date: —, duration: —
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001904157675
Unscheduled inspection
Start date: 2019-12-16, end date: 2019-12-19, duration: —
Authority: Komitet ohotnichego hozyaistva i rybolovstva Saratovskoi oblasti
Purpose of inspection: Execution of a previously issued prescription
# 641903961870
Unscheduled inspection
Start date: 2019-06-28, end date: 2019-06-28, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Saratovskoi oblasti
Purpose of inspection: This audit is conducted in order to verify the fulfillment of the points of the previously issued instruction on the elimination of violations of the law. The objectives of this audit are to establish the compliance of PF NESSI Ltd. with the requirements of regulatory legal acts of the legislation of the Russian Federation in the field of ensuring the sanitary and epidemiological welfare of the population.
# 001801460758
Unscheduled inspection
Start date: 2018-09-20, end date: 2018-09-27, duration: —
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the audit is conducted in order to verify the implementation of paragraphs 113 deadline for the elimination of violations 03032018 of the previously issued regulation dated 29112017 P485124297 on the elimination of identified violations of mandatory requirements due to the expiration of their deadlines, the task of this audit is to implement measures to control and supervise the elimination of PF NESSILTD LLC identified violations of mandatory requirements reflected in the previously issued regulation dated 29112017 P485124297, the deadline for which expired 03032018