Found 7 inspections:

# 471903984981
Unscheduled inspection
Start date: 2019-04-12, end date: 2019-05-17, duration:
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms


# 471902571987
Unscheduled inspection
Start date: 2019-02-21, end date: 2019-03-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Ensuring the observance and protection of the labor rights and freedoms of citizens, including the right to safe working conditions


# 471903982453
Unscheduled inspection
Start date: 2019-02-21, end date: 2019-03-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Verification of labor legislation


# 781801754999
Unscheduled inspection
Start date: 2018-09-27, end date: 2018-10-24, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Planovaya proverka po programme proverok obekta rekonstrukcii usilenie i montazh konstrukcii podzemnoi i nadzemnoi chasti zdaniya


# 471800378346
Unscheduled inspection
Start date: 2018-05-14, end date: 2018-06-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471800403546
Unscheduled inspection
Start date: 2018-05-23, end date: 2018-06-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 781800193131
Unscheduled inspection
Start date: 2018-03-13, end date: 2018-04-09, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Vypolnenie predpisaniya 2216Pr3217 ot 22122017


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.