# 732101437349
Unscheduled inspection
Start date: 2021-12-13, end date: —, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection:
# 732100593578
Unscheduled inspection
Start date: 2021-09-06, end date: 2021-09-08, duration: 3
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: control over the implementation of regulation No. 276 dated 07/01/2021, verification of the elimination by a legal entity of the violations identified in regulation No. 276 dated 07/01/2021, compliance with the regulations of state control (supervision) bodies, municipal control bodies
# 732100296115
Unscheduled inspection
Start date: 2021-06-17, end date: —, duration: 11
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: This inspection is carried out in order to: implement the inspection program dated 04/27/2021, developed on the basis of the notice of postponement of construction dates dated 04/21/2021 (item No. 4 of the inspection program dated 04/27/2021 "Bricklaying of walls from the 2nd to the 4th floors. Installation of floor slabs, staircases and platforms", notice of deadlines from ). The objectives of this audit are: prevention, detection and suppression of violations of the legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer.
7. The subject of this audit is (please note):
compliance with mandatory requirements or requirements established by municipal legal acts;
# 732004485608
Unscheduled inspection
Start date: 2020-08-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 732004753356
Unscheduled inspection
Start date: 2020-06-10, end date: 2020-06-11, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: this audit is conducted in order to verify compliance with the regulation of 17022020 62 The objectives of this audit are to verify that the legal entity has eliminated the violations identified in the regulation of 17022020 62 The subject of this audit is to comply with the regulations of the state control bodies supervision of municipal control bodies
# 732004434910
Unscheduled inspection
Start date: 2020-06-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 732004422990
Unscheduled inspection
Start date: 2020-02-17, end date: 2020-02-17, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: this audit is conducted in order to verify compliance with the regulation of 29112019 615 The objectives of this audit are to verify that the legal entity has eliminated the violations identified in the regulation of 16082019 341the purpose of this audit is to comply with the regulations of the state control bodies supervision of municipal control bodies
# 732004274332
Unscheduled inspection
Start date: 2020-02-17, end date: —, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection:
# 731904003744
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-11-29, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: this audit is conducted in order to verify compliance with the regulation of 16082019 341 The objectives of this audit are to verify the elimination by a legal entity of the violations identified in the regulation of 16082019 341the purpose of this audit is to comply with the regulations of the state control bodies supervision of municipal control bodies
# 731903879175
Unscheduled inspection
Start date: 2019-10-21, end date: 2019-10-21, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: this inspection is carried out in order to implement the inspection program developed on the basis of the notice of the start of construction of the reconstruction of the capital construction facility dated 05092019 1 paragraph 3 of the inspection program The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development committed by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or the technical customer, including including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts.
# 731903798671
Unscheduled inspection
Start date: 2019-10-07, end date: 2019-10-11, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the inspection program developed on the basis of the notice of the start of construction of the reconstruction of the capital construction facility dated 05092019 1 item 1 of the inspection program "Preparatory work" The objectives of this inspection are to prevent, identify and suppress violations of the law committed by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or the technical customer. urban planning activities, including technical regulations and project documentation, The subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 731903861976
Unscheduled inspection
Start date: 2019-10-15, end date: 2019-10-17, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: this inspection is carried out in order to implement the inspection program developed on the basis of the notice of the start of construction of the reconstruction of the capital construction facility dated 05092019 1 item 2 of the inspection program "Access road arrangement" The objectives of this inspection are to prevent, identify and suppress violations of the law committed by the developer, the technical customer, as well as the person carrying out construction on the basis of a contract with the developer or the technical customer on urban planning activities, including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 731902939629
Unscheduled inspection
Start date: 2019-08-15, end date: —, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection:
# 731904003692
Unscheduled inspection
Start date: 2019-08-15, end date: 2019-08-16, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: this audit is conducted in order to verify compliance with the regulation of 29102018 467OC The objectives of this audit are to verify the elimination by a legal entity of the violations identified in the regulation of 29102018 467OC The subject of this audit is to comply with the regulations of state control bodies supervision bodies of municipal control
# 731904003611
Unscheduled inspection
Start date: 2019-08-15, end date: 2019-08-16, duration: —
Authority: Agentstvo gosudarstvennogo stroitelnogo i zhilischnogo nadzora Ulyanovskoi oblasti
Purpose of inspection: this audit is conducted in order to verify compliance with the regulation of 29102018 467OC The objectives of this audit are to verify the elimination by a legal entity of the violations identified in the regulation of 29102018 467OC The subject of this audit is to comply with the regulations of state control bodies supervision bodies of municipal control
# 731800033070
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-02-16, duration: —
Authority: Gosudarstvennaya inspekciya truda v Ulyanovskoi oblasti
Purpose of inspection: Verification of compliance with labor legislation and other regulatory legal acts containing labor law norms